A committee, five copies and a ten thousand rupee draft
20 October 2026
An inter Ministerial Screening Committee decided who got India's coal for nearly two decades, and its paperwork was written down. Applications for a captive block had to go to the Director in the Ministry of Coal in five copies, with a certificate of registration, a document naming the people authorised to sign for the company, certified copies of its Memorandum and Articles of Association, three years of audited accounts, and a project report for the plant the coal would feed. The applicant also had to send a schedule of implementation in the form of bar charts, a schedule of exploration for unexplored blocks, a plan for disposing of the carbon bearing waste from mining and washing, and a demand draft for Rs 10,000 in favour of the Pay and Accounts Officer of the Ministry of Coal. Applications without these accompaniments would be treated as incomplete and rejected. Ministry of Coal, Guidelines for allocation of captive blocks and conditions of allotment through the Screening Committee
Guidelines named the factors that were supposed to decide a contest between rival applicants for the same block. They included the stage of progress and state of preparedness of the project, the net worth of the applicant, the production capacity and maximum recoverable reserve proposed, the date proposed for commissioning the captive mine, the applicant's technical experience, and the recommendations of the administrative ministry and of the state government concerned. Preference would go to the power and steel sectors; within power, to projects of more than 500 MW, and within steel, to plants of more than one million tonnes a year. The guidelines also allowed a number of applicants to form a consortium or a joint venture mining company to share a block in proportion to their assessed requirement of coal. Ministry of Coal, Guidelines for allocation of captive blocks and conditions of allotment through the Screening Committee
An allotment carried conditions. The applicant had to submit an affidavit that all coal mined from the block would be used exclusively in the proposed end use project, and that in case of slippage the block would be de allocated without any liability to the government. The normative ceilings were 36 months from the allocation letter to production in an opencast mine, or 42 months if the area was forest land, and 48 months for an underground mine, or 54 months in forest land. The company had to give a bank guarantee equal to one year's royalty on the mine's assessed capacity within three months of the letter, half of it tied to development milestones and half to guaranteed production, and the guarantee could be encashed in proportion to lapses. Slippage in the time limits, unless the committee agreed otherwise for reasons recorded in writing, could lead to forfeiture of the guarantee or cancellation of the allocation. Ministry of Coal, Guidelines for allocation of captive blocks and conditions of allotment through the Screening Committee
Government accounts present the evolution of the system as a story of tightening. In his August 2012 statement to Parliament the Prime Minister said that since 1993 allocations had been made on recommendations of an inter Ministerial Screening Committee that also had representatives of state governments. Taking into account the increasing number of applicants, the government in 2003 had evolved a consolidated set of guidelines to ensure transparency and consistency. The UPA improved the procedure in 2005 by inviting applications through open advertisements after publishing details of the blocks on offer, along with the guidelines and conditions of allotment. Applications were examined by a broad based committee with representatives of state governments, related central ministries and the coal companies, and were assessed on techno economic feasibility, preparedness, track record, financial and technical capability, and the recommendations of the state government and the administrative ministry. Any administrative allocation involves some judgement, he said, and in this case the judgement was that of the many participants in the committee acting collectively, and there had been no allegations of impropriety in its functioning. Indian Express, PM Manmohan Singh’s statement on coal block allocation
Those who ran the process described it less comfortably. P.C. Parakh, who was Coal Secretary in 2004, told The Economic Times in June 2012 that the existing procedure of awarding blocks through a screening committee was flawed and not free from pulls and pressure. He conceded that there was political pressure on the committee to award mines to certain companies, and said that all kinds of people were canvassing. On 30 July 2004 he wrote that the present system of allocation, even with modifications, would not be able to achieve the objectives of transparency and objectivity. Economic Times, PMO pushed bidding for captive coal mines in 2004, says TKA Nair The Hindu, Coal Secretary warned of “windfall gains” in captive mining allotments in 2004, 2012-03-27
What the audit found about the follow through is as significant as how the blocks were chosen. The CAG's performance audit, countersigned on 11 May 2012, said the Ministry of Coal introduced the system of bank guarantees only in March 2005 and modified it in January 2007, linking half the guarantee to milestones to be achieved before the start of production and half to guaranteed production. The auditors said the delay meant that guarantees could not be made applicable to 46 coal blocks allocated before 2005, and that penalties for missing milestones could not be imposed on 118 blocks allotted before July 2007. In the absence of a method for accounting for guarantees, the ministry could not encash guarantees worth Rs 12.94 crore against six blocks, and as of November 2011 guarantees of Rs 311.81 crore on 15 blocks had lapsed without renewal. CAG, Report No. 7 of 2012-13, Chapter 6: Conclusions and Recommendations (archived copy)
Monitoring was thin as well. The audit said the Coal Controller's Organisation, the nodal agency for the purpose, had not conducted any physical inspection of allocated blocks to check actual progress or production against what the allottees reported, so the correctness of the data they supplied remained unverified. The auditors recommended regular physical inspections. They also looked at the output that the system was supposed to produce. Of 28 producing blocks as of 30 June 2011, ten had time overruns of one to ten years against their normative production schedules, and among 68 non producing blocks whose normative date of production had passed, 47 had overruns of one to five years and four had overruns of more than five and up to ten years. The audit linked these delays to the time taken to get mining leases and other statutory clearances. CAG, Report No. 7 of 2012-13, Chapter 6: Conclusions and Recommendations (archived copy)
A parallel scheme did not involve the Screening Committee at all: the de reservation of blocks that Coal India Limited had held for itself. To increase the supply of coal, the Ministry of Coal de reserved 48 Coal India blocks, of which three were later de allocated and nine stayed unallocated; of the remaining 36, production had still not started in nine although the normative date had passed, and the normative schedules of the other 27 ran beyond July 2011. The auditors concluded that the de reservation had not yielded the desired results. CAG, Report No. 7 of 2012-13, Chapter 6: Conclusions and Recommendations (archived copy)