Monday, 25 August 2014: the judgment

20 October 2026

On Monday, 25 August 2014, a Supreme Court bench of Chief Justice R.M. Lodha and Justices Madan B. Lokur and Kurian Joseph declared the allocation of coal blocks illegal. The New Indian Express reported that the Court held all allocations made from 1993 until 2010, under both the NDA and the UPA governments, to have been made illegally, with an "ad hoc and casual" approach and without application of mind. The bench's judgment ran to 163 pages, and the group of petitions it decided had been filed in 2012 by the advocate M.L. Sharma and the non governmental organisation Common Cause. New Indian Express, All Coal Block Allocations Since 1993 Done in Illegal Manner: SC, 2014-08-25 Times of India, All coal block allocations since 1993 'arbitrary, illegal', rules SC, 2014-08-25

Screening committee allocations were the Court's central finding. LiveLaw reproduced its summary: the entire allocation of coal blocks on the recommendations of the Screening Committee from 14 July 1993, in 36 meetings, and the allocation through the Government dispensation route suffered from the vice of arbitrariness and legal flaws. The words of the judgment, as quoted in the same report, were that the Screening Committee had never been consistent and had not been transparent, that there was no proper application of mind, that it had acted on no material in many cases, and that guidelines had seldom guided it and on many occasions had been honoured more in their breach. The Court said that there was no objective criterion, indeed no criterion at all, for evaluating comparative merit, that the approach had been ad hoc and casual, and that the result was an unfair distribution of national wealth in which common good and public interest had suffered heavily. LiveLaw, Coal Allocation between 1993 and 2009 illegal, arbitrary, non-transparent and were devoid of any procedure, 2014-08-25

A second finding was about the other route. The Court held that allocation through the Government dispensation route, however laudable its object, was also illegal, because it was impermissible under the scheme of the Coal Mines (Nationalisation) Act. It said no State Government or public sector undertaking of a State Government was eligible to mine coal for commercial use, that joint ventures with ineligible firms were impermissible, and that there was no room for a consortium, leader or association in allocation. Only an undertaking with a unit engaged in the production of iron and steel, the generation of power, the washing of coal obtained from a mine, or the production of cement was eligible, in addition to the Central Government and its companies and corporations. LiveLaw, Coal Allocation between 1993 and 2009 illegal, arbitrary, non-transparent and were devoid of any procedure, 2014-08-25

What the judgment did not do came next: it cancelled nothing. The Court said that as the allocations under both routes were arbitrary and illegal, the consequence was the issue still to be tackled, and that to this limited extent the matter required further hearing. The Business Standard recorded that the Court passed no consequential order and that the issues would be considered on 1 September. The Times of India wrote that the allocations were not scrapped but that their fate hung in the balance. New Indian Express, All Coal Block Allocations Since 1993 Done in Illegal Manner: SC, 2014-08-25 Business Standard, Coal block allocations since 1993 illegal: SC, 2014-08-25 Times of India, All coal block allocations since 1993 'arbitrary, illegal', rules SC, 2014-08-25

Ultra mega power projects were carved out by the bench. It said that no challenge had been laid before it to blocks where competitive bidding for the lowest tariff had been held for Ultra Mega Power Projects in accordance with the opinion in the Natural Resources Allocation Reference, and directed that coal blocks allocated to UMPPs would be used only for those projects, with no diversion of coal for commercial exploitation. The Times of India added that the Court termed the government's decision to permit UMPPs to divert coal for commercial use illegal. New Indian Express, All Coal Block Allocations Since 1993 Done in Illegal Manner: SC, 2014-08-25 Times of India, All coal block allocations since 1993 'arbitrary, illegal', rules SC, 2014-08-25

After pronouncing the judgment the bench observed orally that the Attorney General had given the figures of coal blocks but that they were not verified and that state governments had raised objections; the Court suggested a small committee of retired Supreme Court judges to report in the shortest possible time. The Chief Justice said the committee would sort out the data question. New Indian Express, All Coal Block Allocations Since 1993 Done in Illegal Manner: SC, 2014-08-25 Business Standard, Coal block allocations since 1993 illegal: SC, 2014-08-25

Further, the same report observed that the Supreme Court had taken up monitoring of the CBI's work on the allocations after allegations that the agency was under political pressure. The Business Standard recalled that the court had asked the CBI to look into the allegations, had monitored its work for two years through interim status reports, and that the government had itself cancelled several allocations with glaring illegality in that period. Times of India, All coal block allocations since 1993 'arbitrary, illegal', rules SC, 2014-08-25 Business Standard, Coal block allocations since 1993 illegal: SC, 2014-08-25

Next, the judgment also set out the legal background. It recounted that Entry 54 of the Union List provides for the regulation of mines and mineral development to the extent Parliament declares it expedient in the public interest, and that this made a separate legislation imperative, the Mines and Minerals (Regulation and Development) Act of 1957. It recorded that Parliament enacted the Coal Mines (Nationalisation) Act soon after the Coal Mines Management Act, to acquire the coal mines specified in its Schedule so as to ensure the rational, coordinated and scientific development of coal resources, with the ownership and control of such resources vested in the state. It also observed that the declarations under the 1957 Act took the regulation and development of coal mines out of List II Entry 23, so that the states had lost legislative competence over them. Indian Kanoon, Manohar Lal Sharma vs The Principal Secretary on 25 August, 2014

Reuters captured the commercial stakes on the same week: the Court's ruling covered blocks awarded since 1993, and so included blocks awarded to firms like Hindalco and Jindal Steel and Power, and a further hearing was set for the Monday after. Reuters, CBI drops coal scam case against Kumar Mangalam Birla, 2014-08-30