Report No. 7 of 2012 to 2013: what the audit said, in its own order
20 October 2026
Report No. 7 of 2012 to 2013, the Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production in the Ministry of Coal, was tabled on Friday, 17 August 2012, according to the CAG's own listing of the report. The report runs to six chapters and annexures: an overview of coal, the audit framework, augmentation of coal production, allocation of captive coal blocks, production performance of captive coal blocks, and conclusions and recommendations. Its overview put India's geological coal reserve at 2,85,863 million tonnes and said that more than half of the country's commercial energy was met by coal. It gave as the reason for the audit the widening gap between demand and domestic production, the consequent rise in imports, and instances of power capacity lying idle or struggling to expand for want of coal. It added that, although the government had notified certain sectors that could undertake captive mining, the process of allocating coal mines should be objective and transparent. CAG, Report No. 7 of 2012-13, Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, report page
Half of the audit concerned supply from Coal India Limited rather than the private blocks. The Expert Committee on the road map for coal sector reforms, chaired by T.L. Sankar, had recommended in December 2005 that the drilling capacity of the Central Mine Planning and Design Institute Limited be raised to at least 15 lakh metres a year, and the audit found that its expected drilling capacity was only 3.44 lakh metres in 2011 to 2012. It found that the rate of increase in coal production by Coal India during the Eleventh Plan remained far below the target envisaged by the Planning Commission. It attributed the low output to inadequate drilling capacity, a backlog in overburden removal, a mismatch between excavation and transportation capacities, and the low availability and under utilisation of heavy earth moving machinery. The conclusions chapter added that capacity addition projects were delayed by the lack of a coordinated and planned approach among the government agencies handling statutory clearances and land acquisition. CAG, Report No. 7 of 2012-13, Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, report page CAG, Report No. 7 of 2012-13, Chapter 6: Conclusions and Recommendations (archived copy)
Two further findings concerned how coal reached its users. The New Coal Distribution Policy notified by the Ministry of Coal in 2007 was meant to distribute coal to small and medium consumers more effectively, but the audit found that Coal India had no monitoring mechanism to verify the end use of that coal. It also found that the existing washeries of Coal India could not meet the country's requirement of washed coal. The report recommended that the washeries be expedited, noting that Indian coal contains a higher percentage of ash and that washing is of utmost significance for the efficiency of user plants. CAG, Report No. 7 of 2012-13, Chapter 6: Conclusions and Recommendations (archived copy)
Blocks were counted in several ways, depending on who counted and to what date; the CAG's own 194 net blocks to 31 March 2011 is only the first of them. Business Standard's report on the leaked draft spoke of 193 blocks allocated between 1993 and 2009. The Ministry of Coal's list of allocated blocks carries 195 numbered entries, and its 2016 status note counts 218 blocks allocated between 1993 and 2011, the base from which the Supreme Court quashed 214 of 218 in September 2014. The audit's 142 blocks are the narrower set allocated since July 2004, and its Rs 1.86 lakh crore estimate rests on 57 blocks allocated to private parties. This account gives each figure as the body that produced it stated it, and uses 218 for the whole population of blocks. PRS Legislative Research, CAG Performance Audit on the Allocation of Coal Blocks, 2012-08-17 CAG, Report No. 7 of 2012-13, Chapter 6: Conclusions and Recommendations (archived copy) Business Standard, PM under fire, CAG does firefighting on coal report, 2012-03-22 Ministry of Coal, List of allocated coal blocks, 2016 (archived copy) Ministry of Coal, Updated status of coal and lignite blocks allocated during 1993-2011 under the Coal Mines (Nationalisation) Act, 12 September 2016 (archived copy) LiveLaw, Supreme Court quashes 214 coal blocks allocation since 1993, levies penalty of Rs. 295/- per metric, 2014-09-24 The Hindu, Bidding for coal blocks could have yielded gains to government, 2012-08-17 Hindu BusinessLine, How CAG fixed Coalgate loss - The HinduBusinessLine, 2012-09-01
Its conclusions chapter opened by recalling the government's declared mission of "Power to all by 2012". It recommended an assessment of how far that objective had succeeded so that mid course corrections could be made, and observed that the need for power in the country's economic development would remain paramount. It described captive coal mining as a mechanism meant to encourage private participation, given the limits on Coal India's ability to raise production, and to assure supply to the core sectors of power, steel and cement. CAG, Report No. 7 of 2012-13, Chapter 6: Conclusions and Recommendations (archived copy)
Among its recommendations, the audit said the Ministry of Coal should urgently work out the modalities for allocating captive blocks through competitive bidding, to bring objectivity and transparency to allocation and to tap a part of the benefit that accrued to allottees. It said an empowered group along the lines of the Foreign Investment Promotion Board should be constituted as a single window mechanism, with representatives of the central nodal ministries and the state governments, to grant clearances such as the mining lease, mining plan, forest clearance, environment management plan and land acquisition. It recommended a system of incentives to encourage production from captive blocks and disincentives for non performance or poor performance, and regular physical inspection of allotted blocks. The remaining recommendations in the chapter included fixing production targets in line with those of the Planning Commission and synchronising excavation and transportation capacities. CAG, Report No. 7 of 2012-13, Chapter 6: Conclusions and Recommendations (archived copy)