Talabira II: the file as the papers published it

20 October 2026

Business Standard laid out the paper trail on which the Hindalco case rested, giving the sequence as the special court itself drew it. Indalco, an Aditya Birla group company, had long been seeking Talabira II, while Coal India Limited expressed a wish not to allocate the block to private parties and recommended Neyveli Lignite Corporation for its 2,000 MW power plant. A sub committee formed at the 21st meeting of the screening committee on 19 August 2003 favoured allocation to NLC for captive use by itself or with Mahanadi Coalfields, and its report went to Parakh, then Coal Secretary and chairman of the committee, in November 2003. Business Standard, Hindalco block allocation: A tale of two letters, a few reminders and word of caution, 2014-12-17

At its 25th meeting in January 2005 the screening committee considered applications from six companies, including Indalco, Hindalco and NLC, and concluded that NLC was the most deserving. Hindalco was told that it had already been allotted Talabira I for a 140 MW captive plant at Hirakud and a 50 MW plant at Raigarha, neither of which had been set up. The Odisha government very strongly supported NLC's project, but said Hindalco would give maximum value and employment generation and suggested the block go to Hindalco. The committee decided against a separate block for Hindalco and proposed that Talabira II and III be developed as a single large mine allocated to NLC with Mahanadi Coalfields, with coal for Hindalco supplied from it after NLC's 2,000 MW requirement was met. It also proposed amending the guidelines to allow deserving private firms to form joint ventures. Business Standard, Hindalco block allocation: A tale of two letters, a few reminders and word of caution, 2014-12-17

Minutes themselves were published by the Hindu in October 2013. It reported that the minutes of the 25th screening committee meeting of 10 January 2005, which Parakh chaired, showed an absolute rejection of Hindalco's requirement for additional blocks. Hindalco had asked for Talabira II and Bijahan for a 200 MW expansion of its captive plant at Hirakud and for a proposed greenfield aluminium project with a 720 MW plant at Lapanga. The committee questioned why Hindalco applied for a second block when it had been allocated Talabira I on 25 February 1994 and had failed over 11 years to carry out the end use project for that block. Of the Aditya Aluminium project, the minutes recorded that it was perhaps too early to ask for a block for a project planned for 2010, and a later note recorded that the project had a long term coal linkage of 3.06 million tonnes a year from Mahanadi Coalfields that would meet the requirement of its 650 MW plant. The Hindu said the rejection was approved on 1 March 2005 at the 27th meeting, and that the government nonetheless allocated Talabira II to Mahanadi Coalfields, NLC and Hindalco on 10 November 2005. The Hindu, U-turn on allocation of coal block to Hindalco points to PM, 2013-10-17

Minister of State Dasari Narayana Rao forwarded Parakh's recommendation to the Prime Minister, who was also holding charge of the Coal Ministry, in April 2005, and Singh approved the recommendations in June 2005. In June 2005, the paper recorded, Parakh observed that the ministry must now start issuing orders of allocation and complete the work by July 2005 in respect of all the screening committee meetings held so far. Business Standard, Hindalco block allocation: A tale of two letters, a few reminders and word of caution, 2014-12-17

Meanwhile letters had arrived. Birla wrote to the Prime Minister on 7 May 2005 asking for Talabira II, and the Prime Minister made a note on it seeking a report from the Coal Ministry. A letter from the PM's side went to Parakh on 25 May 2005, and the PMO sent a reminder on 16 June. Birla sent an identical second letter on 17 June, on which the Prime Minister's private secretary, B.V.R. Subramanyam, noted that the Prime Minister desired the matter be pursued on priority so that a decision was reached on this long pending matter and its employment and revenue potential fully achieved. That letter was forwarded to Parakh on 24 June, with a request for a report by 28 June. Business Standard, Hindalco block allocation: A tale of two letters, a few reminders and word of caution, 2014-12-17

Business Standard summarised on 16 December 2014 the Prime Minister's own version of these events: that the decision "differed from the earlier recommendation of the Screening Committee" and was made after a representation reached the PMO from one of the parties and was referred to the Coal Ministry. He said Birla was then non executive chairman of Hindalco and had written on 7 May 2005, that he asked Birla to get a report from the Coal Ministry, and that Birla repeated the request in June. In August 2005 the ministry replied that the screening committee had recommended NLC and not Hindalco because adequate coal linkages had been provided to Hindalco from Mahanadi Coalfields long ago and Hindalco had not used the coal. Birla's contention was that his company had been the first to apply, in 1996, that the earlier linkage was unused because the related bauxite mine lease had not materialised, and that the Odisha government favoured Hindalco over NLC. Business Standard, Manmohan Singh's account of the Hindalco coal block allocation, 2014-12-16

Then came the letter of 17 August 2005 from Odisha's Chief Minister Naveen Patnaik. According to the PMO's statement, he gave "topmost priority" to Hindalco and strongly supported its case, on the ground that aluminium plants generate more jobs and wealth than independent power plants. On 29 August 2005 the PMO returned the ministry's recommendation not to allocate the block to Hindalco and asked it to re examine the matter in the light of Patnaik's letter. In September 2005 the ministry resubmitted its recommendation, proposing to allocate Talabira II and III as a single mine through a joint venture of Mahanadi Coalfields, NLC and Hindalco in the ratio 70:15:15. The ministry's own figure was that NLC's satisfaction level would be 29 per cent of its requirement and Hindalco's 81.5 per cent. One of its reasons was that NLC should not be dropped as it was a central PSU already recommended by the screening committee, and that Hindalco's case was strongly recommended by the state government and it was an early applicant. Business Standard, Manmohan Singh's account of the Hindalco coal block allocation, 2014-12-16

Few newspapers matched the detail with which the special court's own order of 11 March 2015 reproduced the file. It recorded that Talabira-II was a much sought after block: Indal applied for it in 1996, Hindalco on 26 August 1997 and Neyveli Lignite Corporation on 8 August 2003. A note recording Birla's submission, quoted later in the same order, gives 16 August 1996 as the date on which Hindalco first applied for the block, and the order does not reconcile the two dates. On 17 February 2003, it said, the Secretaries of Coal and Power, with the chairmen of NLC and Coal India present, had agreed that NLC and NTPC would each build a 2,000 MW project in the Ib Valley, and NLC identified Hirma in Jharsuguda district, beside the block, for its plant. In December 2004, on Parakh's orders, applicants were asked to supply information in a prescribed Agenda Form covering the blocks applied for, track record, end use projects, project status and earlier allocations. Five blocks were on offer, Utkal-A, Radhikapur, Bijahan, Utkal-F and Talabira-II, and six companies applied for Talabira-II: Indian Aluminium and Hindalco together, Shri Mahavir Ferro Alloys, Orissa Sponge Iron, Orissa Power Generation Corporation, Mundra Special Economic Zone and NLC. Special CBI Court, order of 11 March 2015 in CBI v. P.C. Parakh and others, RC 220 2013 E 0011 (Rediff copy)

Minutes of the 25th meeting, as the order quotes them, record the Orissa government's representative supporting NLC's request while adding that Hindalco's aluminium project would add maximum value and employment. The Ministry of Power's representative very strongly supported allocation to NLC, and NLC said its pithead plant was expected to generate power at Rs 1.50. The chairman of the screening committee observed that energy intensive processes should be taken up where power tariffs are lower, and that the energy intensive part of an aluminium project could be outsourced. Special CBI Court, order of 11 March 2015 in CBI v. P.C. Parakh and others, RC 220 2013 E 0011 (Rediff copy)

Quoted in the order also are the notes that moved the file in 2005. When Birla's letters reached the ministry, the section officer Premraj Kuar recorded his difficulty in acceding to Hindalco's request and put up a draft office memorandum giving three reasons: that Hindalco's Aditya Aluminium project already had a coal linkage of 3.06 million tonnes a year granted in October 2001 and had yet to materialise, that the sub committee had recommended Talabira-II for NLC, and that the 25th meeting had identified the block for NLC. Parakh did not approve the memorandum. The PMO sent reminders to the ministry on 16 June, 24 June, 29 June and 6 July 2005, and its joint secretary Javed Usmani and deputy secretary K.V. Pratap also pursued the ministry by telephone at least six times, the order says. Special CBI Court, order of 11 March 2015 in CBI v. P.C. Parakh and others, RC 220 2013 E 0011 (Rediff copy)

Parakh's note of 8 to 11 August 2005 recorded that Birla had met him in the middle of July and listed the reasons Birla gave: that Hindalco was the first applicant, that the earlier linkage from Mahanadi Coalfields could not be used because the lease of the connected bauxite mines had not been obtained, that the Orissa government preferred Hindalco, and that Mahanadi could not honour earlier linkages given the shortage of coal in its area. The two options Parakh proposed in that note did not name NLC. Pratap's note of 12 August recommended that Talabira-II go to NLC only, because a decision to allocate it to NLC had already been taken and because the block being fully explored was not reason enough to reverse an earlier screening committee decision, and Usmani noted that it would be appropriate for the Prime Minister to dispose of the issue after considering the views of the Minister of State. Minister of State Dasari Narayana Rao's note of 16 August said Hindalco had written on 18 May 2005, that Birla had also discussed the issue with him, and that his own suggestion was to consider making coal available from the block to Hindalco at transfer price. Special CBI Court, order of 11 March 2015 in CBI v. P.C. Parakh and others, RC 220 2013 E 0011 (Rediff copy)

By 9 September 2005 a note from the ministry's director, Sujit Gulati, put the satisfaction levels under the proposed 70:15:15 arrangement at 29 per cent for NLC and 81.5 per cent for Hindalco, against an average of about 85 per cent in the Mahanadi area. Parakh's note of 12 September said the arrangement seemed reasonable and would meet about 80 per cent of Hindalco's requirement, and Rao signed it on 16 September without comment. On 21 September Pratap noted that the 70:15:15 shares did not match the guidelines the Prime Minister had approved on 9 June 2005, under which the equity of NLC and Hindalco would be 22.5 and 7.5 per cent, and Usmani noted that the arrangement would need a relaxation of those guidelines and that the Orissa government's strong recommendation had to be given due consideration. T.K.A. Nair approved the ministry's recommendation on 27 September and the Prime Minister on 1 October 2005, and Pratap communicated the approval on 4 October. The allotment letter for Talabira-II and III went out on 10 November 2005 jointly to Mahanadi Coalfields, Hindalco and NLC, on the condition that the joint venture company be formed with the approval of the Cabinet. Special CBI Court, order of 11 March 2015 in CBI v. P.C. Parakh and others, RC 220 2013 E 0011 (Rediff copy)

Aftermath is in the same order. NLC's chairman and managing director, S. Jayaraman, wrote that a 15 per cent share would be inadequate for the 2,000 MW plant, and the ministry allotted NLC a further linkage of 2.31 million tonnes a year by an order of 28 July 2006. At a meeting on 26 June 2006 attended only by Hindalco's representatives, the ministry's minutes recorded that signing the joint venture agreement was taking a long time and that the government was likely to review the allocation if it was not feasible. Special CBI Court, order of 11 March 2015 in CBI v. P.C. Parakh and others, RC 220 2013 E 0011 (Rediff copy)

Read together, the papers give Singh's role in separate steps. He approved the guidelines on 9 June 2005, and the Business Standard placed his approval of the screening committee's recommendations in June 2005. The order records his approval of the ministry's recommendation on 1 October 2005, five months after Birla's first letter of 7 May, and the allotment letter followed on 10 November 2005, the date the Hindu gave for the allocation. Special CBI Court, order of 11 March 2015 in CBI v. P.C. Parakh and others, RC 220 2013 E 0011 (Rediff copy) Business Standard, Hindalco block allocation: A tale of two letters, a few reminders and word of caution, 2014-12-17 Business Standard, How Manmohan Singh became 'conspirator number 3' in the Hindalco case, 2015-03-11 The Hindu, U-turn on allocation of coal block to Hindalco points to PM, 2013-10-17