Sally Ride had seen this before. As the board's work progressed, Ride, the only member who had also sat on the commission that judged the Challenger disaster, observed that there were "echoes" of that accident in this one, and the parallel began at the level of the questions themselves. The Rogers Commission had been driven by two: why did NASA keep flying with known O ring erosion, and why, on the eve of launch, did its managers decide that flying in unprecedented cold was an acceptable risk despite their own engineers' objections? Substitute foam for O rings and an ignored photograph for a pre launch teleconference, and both questions ask themselves about STS 107. CAIB Report Vol. 1: 8.1 Echoes of Challenger (2003-08-26)

Seventeen years earlier, another accident had broken a myth. Through the early 1980s NASA had sold the shuttle as an operational system, safe enough to carry legislators and a high school teacher, and the illusion died on the morning of 28 January 1986, when Challenger was destroyed seventy three seconds into its twenty fifth mission by the failure of an O ring seal in one of its solid rocket boosters, taking its crew of seven. CAIB Report Vol. 1: 1.5 The Challenger Accident (2003-08-26)

The Rogers Commission, appointed by President Reagan and named for its chairman, former Secretary of State William Rogers, discovered that engineers and managers had vigorously debated the launch's wisdom the night before, in the cold, and that more senior NASA managers were unaware of the debate. Its report of 6 June 1986 found that the drive to declare the shuttle operational had put enormous pressure on the system and stretched its resources to the limit, and it ordered a redesigned booster joint, an independent safety office reporting to the administrator, and structural changes in management. The night before that last launch, the commission found, thirty four people in three locations had joined a teleconference that ran from 8:45 to 11:15 p.m., with the contractor's engineers recommending a delay; with no ground rules for so unprecedented a reconsideration, the participants fell back on the centralized, procedure bound model of a readiness review, and the decision to accept the risk and fly was made inside that single room of voices. NASA did not fly again for thirty two months. CAIB Report Vol. 1: 8.5 History as Cause: Two Accidents (2003-08-26) CAIB Report Vol. 1: 1.5 The Challenger Accident (2003-08-26)

Both accidents shared, beneath the hardware, a process the sociologist Diane Vaughan, whose account of Challenger the Columbia board drew on, named the normalization of deviance; the board's own section title for the comparison called both accidents failures of foresight, a phrase borrowed from the sociologist Barry Turner's classic study of man made disasters. In neither case was the fatal anomaly a surprise; in both, the first engineering decision to fly with the flaw was the turning point. "As a result of this new classification," the Columbia board wrote, "subsequent incidents of O ring erosion or foam debris strikes were not defined as signals of danger, but as evidence that the design was now acting as predicted." Engineers and managers, the report went on, "incorporated worsening anomalies into the engineering experience base, which functioned as an elastic waistband, expanding to hold larger deviations from the original design." CAIB Report Vol. 1: 8.2 Failures of Foresight (2003-08-26)

In both situations, the board observed, every new fact was weighed and interpreted against past experience; the formal categories and cultural beliefs of the organization supplied the frame. Vocabulary did the quiet work. Foam damage, a violation of the vehicle's design requirements, came to be filed under the reassuring label "in family," the board noted, adding flatly: "'In family' was a strange term indeed for a violation of system requirements." And in one respect Columbia was worse than Challenger: where booster engineers before 1986 had left a paper trail of escalating alarm, the board uncovered no such trail of rising concern about foam in the years before STS 107. In both cases the engineering analyses were incomplete and inadequate, and in both, "engineers understood what was happening, but they never understood why." The shapes of the two failures mirrored each other, too. Challenger's was one tightly structured teleconference, completed in hours among thirty four engineers and managers; Columbia's was the opposite, sixteen days of decentralized, loosely organized discussion in which working groups and email chains formed spontaneously, while the decisions that mattered drifted upward into informality. CAIB Report Vol. 1: 8.5 History as Cause: Two Accidents (2003-08-26) CAIB Report Vol. 1: 8.2 Failures of Foresight (2003-08-26)

Behind the culture stood money. NASA's budget had fallen from nearly four percent of federal spending at Apollo's height to one percent or less by the shuttle era, and in 1990, after the Hubble mirror embarrassment and shuttle problems, a White House chartered committee chaired by the aerospace executive Norman Augustine concluded that the agency "is currently over committed in terms of program obligations relative to resources available, in short, it is trying to do too much, and allowing too little margin for the unexpected." CAIB Report Vol. 1: 5.3 An Agency Trying to Do Too Much With Too Little (2003-08-26)

Augustine's committee recommended real budget growth of about ten percent a year, to a peak near $30 billion a year in 1990 dollars by 2000; translated into actual fiscal year 2000 dollars, that would have meant a NASA budget above $40 billion. The real figure was $13.6 billion. Over the decade from 1993 to 2002, while overall discretionary spending grew a quarter in purchasing power and non defense spending grew forty percent, NASA's budget lost thirteen percent of its buying power. CAIB Report Vol. 1: 5.3 An Agency Trying to Do Too Much With Too Little (2003-08-26)

Shuttle money fell harder than NASA money. The outgoing administration requested $4.128 billion for the program in fiscal 1993; five years later the request was $2.977 billion, a 27 percent cut, and the fiscal 2003 request of $3.208 billion still stood 22 percent below where the decade began. Adjusted for inflation, the program had lost roughly forty percent of its purchasing power in ten years, against thirteen percent for the agency as a whole, while the flight rate, the station commitments and the promises all stayed. CAIB Report Vol. 1: 5.3 An Agency Trying to Do Too Much With Too Little (2003-08-26)

One passage of the Augustine report reads now like a letter addressed specifically to 2003. Its authors warned that without change "we are likely to lose another Space Shuttle in the next several years," calling the shuttle the weak link of the civil space program, "unpleasant to recognize, involving all the uncertainties of statistics, and difficult to resolve." CAIB Report Vol. 1: 5.3 An Agency Trying to Do Too Much With Too Little (2003-08-26)

Into this squeezed agency arrived a new fixed star. In mid 2001, with the space station over budget and behind schedule, NASA adopted a plan to make the station credible to the White House and Congress; the station program and NASA were, in the board's words, on probation, and the proof of rehabilitation was a date: 19 February 2004, the launch of STS 120 carrying the Node 2 module, which would bring the station to "U.S. Core Complete" status. The station program had run $4 billion over its projected budget when the new administration capped it at a reduced "U.S. Core Complete" configuration, and NASA's managers treated the date as the endorsement of their whole approach; suggestions that it would be difficult to meet were brushed aside. Miss the date, and the agency risked losing support for the station's growth. CAIB Report Vol. 1: 6.2 Schedule Pressure (2003-08-26) CAIB Report Vol. 1: 5.7 The Return of Schedule Pressure (2003-08-26)

By late summer 2002, slips across the manifest had compressed the path to that date into a demand for ten flights in less than sixteen months. Days of schedule margin became the metric by which both the shuttle and station programs were judged; in the program managers' monthly briefings to O'Keefe, the margin to the Node 2 date typically occupied more than half the slides. To claw back time, testing at Kennedy was reduced, more work was stacked in parallel, and a third shift was planned for 2003. CAIB Report Vol. 1: 6.2 Schedule Pressure (2003-08-26)

Headquarters mailed its managers a computer screensaver showing a clock counting down to 19 February 2004. Employees traced the date's grip to the new administrator, who had proposed the station management plan while at the White House budget office; one worker's reflection, that the date "just seemed like an arbitrary date," captured a workforce that believed safety was being squeezed, even as upper management insisted there was no undue pressure. The board weighed both answers and stated which it believed: "The weight of evidence supports the workforce view." CAIB Report Vol. 1: 6.2 Schedule Pressure (2003-08-26)

STS 107 never flew to the station, and it was squeezed anyway. Its own two years of delays had been caused largely by station work taking priority; the fleet grounding and crew rotation arithmetic that shaped its final slot were station arithmetic; and the high pressure atmosphere, the board found, "unquestionably affected Columbia." The schedule did not strike the wing. It taught the people managing the flight which questions cost too much to ask. CAIB Report Vol. 1: 6.2 Schedule Pressure (2003-08-26)

None of it was a secret inside the agency's own manuals. NASA policy dictated that safety programs sit high enough, with enough authority and seniority, to maintain independence; in reality, the board wrote, that demands "a more independent status than NASA has ever been willing to give its safety organizations, despite the recommendations of numerous outside experts over nearly two decades, including the Rogers Commission (1986), General Accounting Office (1990), and the Shuttle Independent Assessment Team (2000)." Headquarters dictated what must be done, not how; the operational premise that followed was that safety was the responsibility of the very program and project managers whose schedules it was supposed to constrain. CAIB Report Vol. 1: 7.4 Organizational Causes: A Broken Safety Culture (2003-08-26)

Information itself was mangled on the way up. The Debris Assessment Team's conclusions reached the Mission Evaluation Room as PowerPoint slides, and Edward Tufte of Yale, the information presentation scholar who had studied communication failures in the Challenger case, examined those slides for the board and showed how the format had buried the key uncertainties. And the rawest signals never arrived at all: the emails in which engineers at Johnson and Langley poured out the depth of their concern, their questions and the actions they wanted taken did not reach the Mission Management Team. CAIB Report Vol. 1: 7.5 Organizational Causes (2003-08-26)

The safety organization that should have pushed back had been hollowed into an observer role. Its structure was worse than thin: at Kennedy, the safety organization had been decentralized into the Shuttle Processing Directorate itself, making oversight still more dependent on the program it watched; at Johnson, the Space Shuttle Division Chief answered to the center, the shuttle program and headquarters safety all at once, a conflict of interest the board called "a single point of failure without any checks or balances," and a March 2001 audit by NASA's own Inspector General had made the same point. It lacked capability and resources independent of the shuttle program, the board found, and so it was not an effective voice on the technical questions of STS 107: "The safety personnel present in the Debris Assessment Team, Mission Evaluation Room, and on the Mission Management Team were largely silent during the events leading up to the loss of Columbia. That silence was not merely a failure of safety, but a failure of the entire organization." CAIB Report Vol. 1: 7.4 Organizational Causes: A Broken Safety Culture (2003-08-26) CAIB Report Vol. 1: 7.5 Organizational Causes (2003-08-26)

None of this, in the board's reading, belonged only to NASA. The constraints under which the agency operated were set by the White House and Congress, whose decisions about budgets and mandates shaped what the shuttle program became, and the board said so to their faces. "History is not just a backdrop or a scene setter," the report insists. "History is cause. History set the Columbia and Challenger accidents in motion." CAIB Report Vol. 1: 8.1 Echoes of Challenger (2003-08-26)

Its warning about the future is the sentence the whole volume was written to support. Despite all the changes after Challenger and all of NASA's achievements since, the institutional causes of that accident had not been fixed, and "the Board strongly believes that if these persistent, systemic flaws are not resolved, the scene is set for another accident." Nor could the fix be a sacrifice of individuals: NASA's problems, the board wrote, "cannot be solved simply by retirements, resignations, or transferring personnel." CAIB Report Vol. 1: 8.1 Echoes of Challenger (2003-08-26)