The medal of shame

14 November 2026

The reckoning arrived in two official volumes. The first came from a High Level Committee the Prime Minister appointed as the confetti was still being swept up, chaired by V K Shunglu, a former Comptroller and Auditor General, to examine the organisation and conduct of the Games. Its reports through 2011 diagnosed a single disease with many symptoms. The organising committee, it wrote, was synonymous with its chairman. It found "extreme concentration of powers at the top", a general body of 500 members too unwieldy to govern, an executive board it called subservient, and key decisions taken by "a handful of powerful loyalists of the Chairman". It named the conflict of interest built into the structure: senior officials of the Indian Olympic Association holding senior positions in the organising committee, the arrangement this file described in its second chapter. It found recruitment to key positions that ignored merit, senior figures with questionable records and past vigilance cases, dissent not tolerated, and a "coterie style" of management so feud ridden that the feuds themselves delayed the work. Across the projects it examined, the committee upbraided government agencies for losses of over Rs 1,600 crore. Shunglu report faults with Kalmadi, Bhanot over CWG contracts, The Hindu (2011-11-26) Report of the High Level Committee on Commonwealth Games 2010, V K Shunglu chair, Cabinet Secretariat

The second volume was heavier, in every sense. In August 2011 the Comptroller and Auditor General tabled in Parliament a performance audit of the Games that ran to some seven hundred pages, and The Hindu's headline called it a medal of shame pinned on Delhi and the Centre alike. The audit's power was not in any single number but in a sentence of method, the most quoted passage of the report, in which the auditor described "the modus operandi observed over the entire gamut of activities leading to the conduct of the Games" as "inexplicable delays in decision making, which put pressure on timelines and thereby led to the creation of an artificial or consciously created sense of urgency." Because the target date was immovable, the report went on, those delays "could only be overcome by seeking, and liberally granting, waivers in laid down governmental procedures. In doing so, contracting procedures became a very obvious casualty. Many contracts were then entertained based on single bids, and in fact, some of them were even awarded on nomination basis." CAG pins 700 page medal of shame on Delhi, Centre, The Hindu (2011-08-06) Report of the Comptroller and Auditor General of India on XIXth Commonwealth Games 2010, Performance Audit Report No. 6 of 2011

Then the auditor drew the conclusion that officials usually shrink from, and printed it: "A conclusion from such action which seems obvious is that this could indeed have even been an intended objective! Eliminating competition led to huge avoidable extra burden on the exchequer." Read it again. The supreme audit institution of India looked at the most expensive public event in the country's history and said, on the record, that the chaos may have been the method: that urgency was manufactured so that procedure could be waived, and procedure was waived so that competition could be eliminated, and competition was eliminated so that chosen vendors could charge what they liked. The treadmill and the timing system of the previous chapter were not accidents of haste. They were products of design. CAG pins 700 page medal of shame on Delhi, Centre, The Hindu (2011-08-06)

The audit also put its finger on the lost years. There had been a seven year window from the award in November 2003 to the opening in October 2010, the report noted, and the first three of them were squandered: "The time window from November 2003 to mid 2006, which could have been effectively used for planning, clearances and approvals, was wasted. The OC itself was registered only in February 2005." Master schedules and operational plans arrived late, and the committee's internal controls were so inadequate, its documentation so poor, that the auditor said it was "unable to derive assurance as to either the authenticity or the completeness of records." On the overlays, the report said the contracts were signed at exorbitant rates causing huge financial loss, and that although the true total loss could not be fully quantified from the available records, indicators, comparisons of item wise rates across clusters, vendors and the rates the same firms declared to Customs, pointed the same way. CAG pins 700 page medal of shame on Delhi, Centre, The Hindu (2011-08-06)

Between them, the two reports fixed the vocabulary in which the Games would be judged. Shunglu gave the political system its diagram of the machine: one man, two chairs, a subservient board, loyalists in the secretariat. The CAG gave it the machine's operating manual: delay, urgency, waiver, single bid, nomination. Neither report was a charge sheet, and neither could punish anyone. What they did instead was convert rumour into record. After August 2011, nobody who claimed the Games had merely been mismanaged could be taken seriously, because the auditor had already answered them: the management was the message.

Shunglu's arithmetic was as specific as its anatomy. On the venues alone it put the cost of delay in completing construction at Rs 800 crore, found financial oversight failures that handed contractors an undue gain of over Rs 250 crore, and counted an estimated Rs 574 crore of wasteful expenditure on certain types of assets. It did not stop at the organising committee. It named a class of senior functionaries, the chairman of the New Delhi Municipal Council, the vice chancellor and chief finance officer of Delhi University, the director general of the Central Public Works Department, senior officers of the development authority and of Engineers India Limited, and then wrote the sentence the system had been dreading: "The malaise runs deep and cannot be dismissed as a one off aberration for which relatively junior functionaries alone can be held responsible." Its successive reports went steadily up the ladder: the first recommended action against the chief executive of Prasar Bharati over the host broadcasting deal; the second and third named, respectively, the Lieutenant Governor of Delhi and the Chief Minister herself. Shunglu report faults with Kalmadi, Bhanot over CWG contracts, The Hindu (2011-03-31)

One of its referrals mattered more than the rest, and it was aimed at the contracts that would later close around Kalmadi himself. The committee called the award of three consultancy contracts to Event Knowledge Services "dubious" and said flatly: "This is a fit case for reference to the CBI and the ED. They would have to investigate the ownership of EKS Private Limited, Mauritius and trace the flow of funds from the OC to EKS private limited and onwards to other recipients." The criminal cases that finally collapsed in 2025, fourteen years later, were the direct descendants of that paragraph. Shunglu report faults with Kalmadi, Bhanot over CWG contracts, The Hindu (2011-03-31)

Before either report landed, the vigilance commission had already published the working drawings of the racket. Its July 2010 examination of sixteen Games projects, with a revenue implication of more than Rs 2,500 crore, confirmed what it called an officer, engineer, contractor nexus that "minted money by delaying the award of contracts till the last minute so that an alibi could be found to jack up cost and assign the work to favourites." One year before the CAG wrote of a consciously created sense of urgency, the CVC had already named the same machine in its own words. Its case file on the street lighting contract was pure theatre: the winning bidder's figures had been altered after the auction, cut or overwritten to sit just below the nearest rival, adding Rs 3.6 crore to a Rs 35 crore contract. Its engineers' findings were worse: twelve concrete core samples failed the twenty eight day strength test at an independent laboratory, the cement content in the slabs was far below what was prescribed and claimed, and the testing records had been forged with the collusion of the supervising civic agency. On the streetscaping that had torn up every pavement in the capital, the commission's verdict was that the agencies had taken up the work "without ascertaining the need" for it, and that "the main purpose of aesthetics could not be achieved due to poor quality control." Money spent, roads dug, ugliness delivered. CVC X-rays 16 Commonwealth Games projects, detects brazen corruption, The Economic Times (2010-07-30)

Release day theatre matched the contents. The deputy CAG, Rekha Gupta, faced the cameras in New Delhi with the 700 page volume, and the headlines wrote themselves from the audit's own vocabulary: siege, urgency, waiver, nomination. What gave the coverage its force was that the auditor refused the comfort of vagueness. Where a cautious report might have lamented capacity constraints and lessons learned, this one walked the reader through the mechanism step by step and then printed the exclamation marked conclusion about intended objectives. Indian audit reports are not usually quotable. This one was quoted for fifteen years. CAG pins 700 page medal of shame on Delhi, Centre, The Hindu (2011-08-06)

Its most quotable findings were about culture rather than contracts, and they read like a description of a court rather than an administration. "The tone at the top created a situation where wrong doing was common and best practices were not encouraged," the Shunglu report said. "Accountability, internal and external was not the norm." It found recruitment to the secretariat and senior leadership untethered from merit, key posts filled with persons of questionable integrity and past vigilance cases, government instructions flouted in postings to sensitive positions, and dissent not tolerated. It described a vigilance and internal audit function that provided no watchdog function at all. And it found that the committee's internal feuds were not incidental to the delays but a driver of them, spilling over "to affect the smooth operations and monitoring of the progress of work." A machine built to deliver one fortnight had been captured so completely that its internal wars were allowed to endanger the fortnight itself. Shunglu report faults with Kalmadi, Bhanot over CWG contracts, The Hindu (2011-03-31)