A well like Macondo is finished in stages. The crew drills a section of hole, lines it with steel casing, and cements the casing in place; then it drills deeper and repeats. The last section, the one crossing the oil and gas reservoir itself, is the production casing, and the decisions BP made about it in April 2010 sit at the center of everything that followed. Each one was defensible in isolation. Each one saved time or money. Together they built a well with almost no margin for error. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo Well-Deepwater Horizon Blowout: Lessons for Improving Offshore Drilling Safety - National Academy of Engineering (2011)

To understand those choices, start with the rock. Macondo's reservoir sat under such delicate pressure conditions that the well could be kept in balance only inside a razor thin band: too little mud weight and the formation pushed gas into the well; too much and the mud fractured the rock and drained away. A kick on March 8 had, in the words of BP's own engineers, "completely changed" the well's forward design, "rapidly," forcing extra casing strings that had not been in the plan. Then, on April 9, with the bit into the pay zone at 18,193 feet below sea level, the mud pressure exceeded the strength of the formation and the well started drinking the mud. The crew sealed the fracture with 172 barrels of lost circulation material, but BP's engineers knew what the event meant: they had "run out of drilling margin." The well was stopped 167 feet later, at 18,360 feet, more than 2,000 feet short of its planned depth. The lost returns had come all through the drilling, once in mid February, four times in March and three times in April; in all, the well drank approximately 16,000 barrels of mud, costing BP more than $13 million in rig time and materials. Every decision that followed was made inside that narrow band, with a fragile well that could be lost in either direction. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17)

First came the design of the production casing itself. BP's plan called for a long string, a single run of steel pipe hanging from the wellhead on the seafloor all the way to the bottom of the well, 13,000 feet below. The alternative was a liner, a shorter casing hung from the bottom of the previous casing and tied back later, which gave the well an extra mechanical seal against gas rising up the outside of the pipe. In early April, with drilling problems mounting, the engineers briefly considered switching to a liner. The change had people scrambling. Guide recounted that Vidrine had complained about the churn: "[T]here [have] been so many last minute changes to the operation that the WSL's have finally come to their wits end," Guide recounted. "The quote is 'flying by the seat of our pants.'" Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17)

On April 14 the engineers met in Houston and settled it: they would run the long string. The management of change document said the long string provided the best "well integrity case for future completion operations" and the best economic case, and among the motivations was a desire to save $7 million to $10 million in future completion costs. The National Academy of Engineering later listed the choice of a long string in a deep, high pressure well with multiple hydrocarbon zones, instead of a liner over the uncased section, as one of the decisions that increased the risk of the blowout. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo Well-Deepwater Horizon Blowout: Lessons for Improving Offshore Drilling Safety - National Academy of Engineering (2011)

Next came cement. The crew had to pump cement down the casing and up the narrow annulus between the pipe and the rock, and the standard way to prepare the hole was to circulate the drilling mud completely around, a full bottoms up, to sweep out debris and contaminated mud. Halliburton's own standard called for at least one full bottoms up before a cement job, which at Macondo meant circulating 2,760 barrels of mud, an operation that could take 12 hours. After a lost circulation event on April 9 showed how fragile the well's pressure margins were, BP cut the volume back again and again. To compensate for the short circulation, the team asked Halliburton to pump extra spacer ahead of the cement. In the end, on the afternoon of April 19, the crew circulated about 350 barrels before pumping cement, roughly an eighth of a bottoms up. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo Well-Deepwater Horizon Blowout: Lessons for Improving Offshore Drilling Safety - National Academy of Engineering (2011)

Then came the centralizers. Cement seals only if the casing sits in the middle of the hole; a pipe leaning against the rock leaves a channel of mud up one side that gas can travel. Centralizers, spring like collars clamped around the pipe, keep it centered. Halliburton's computer modeling said the casing needed 21 centralizers to achieve the required standoff; BP had six centralizer subs on the rig. When Halliburton engineer Jesse Gagliano flagged the risk on April 15, BP's drilling engineering team leader Gregg Walz ordered 15 more centralizers flown out, the most a single helicopter could carry, writing to Guide that "we needed to be consistent with honoring the model." Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17)

Then the plan reversed. The 15 additional centralizers were slip on models left over from BP's Thunder Horse project, and Guide worried they could snag while the casing was being run and leave the pipe stuck above the wellhead. On April 16, after the helicopter carrying them had already landed, BP decided not to install them. Operations engineer Brett Cocales spelled out the trade in an email to Brian Morel: "I would rather have to squeeze than get stuck above the WH [wellhead]. So Guide is right on the risk/reward equation." A squeeze job is the remedy for a bad cement job: perforate the casing and force cement through the holes. In other words, the team had weighed the risk of a stuck pipe against the risk of a failed cement job, and chosen the failed cement job as the one they could live with. Neither BP nor Halliburton appears to have considered that poor centralization could raise the chance of a blowout; the worst case they discussed was remedial cementing. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17)

The Chief Counsel's report later captured the decision culture in one email: after Guide settled on six centralizers despite the channeling risk, one BP engineer wrote to another team member, "But who cares, it's done, end of story, [we] will probably be fine and we'll get a good cement job." The same report found that Transocean's crew was never told Halliburton had recommended more than the six centralizers that were used. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17)

Gagliano learned of the decision from a Halliburton cementer on the rig and asked BP to confirm it. Getting no reply, he ran a new model on April 18 with six centralizers. It predicted poor centralization, mud channeling and "SEVERE" gas flow potential. He sent the results to the BP team; the cement job went ahead anyway with six centralizers. Gagliano ran his models from Houston; Halliburton kept an office in BP's own building there, near the engineers he was warning. The men who actually pumped the Macondo cement, Vincent Tabler and Christopher Haire, were aboard the rig that week and were still aboard when it blew. Morel, meanwhile, had been rearranging the six centralizer subs on his own casing tally, telling Cocales, "We can argue this one out after we get the actual vs model data and see how it reacts." No one ever ran a model of the arrangement actually installed: BP never requested one, and Halliburton never ran one. The National Academy of Engineering would later record, drily, that the crew decided only six centralizers were needed "even though modeling results suggested that many more centralizers would have been needed." Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo Well-Deepwater Horizon Blowout: Lessons for Improving Offshore Drilling Safety - National Academy of Engineering (2011)

Cement came next. The well's fragile geology ruled out a normal heavy slurry, so Halliburton designed a foamed cement: a base slurry of 16.74 pounds per gallon, lightened to an average of 14.5 pounds per gallon by injecting nitrogen bubbles into it. Foamed cement is delicate. If the bubbles migrate or escape, the slurry separates and never sets properly. Halliburton's own laboratory in Broussard, Louisiana, had run two foam stability tests on the Macondo design in February. In the first, the top and bottom of the cured sample weighed 16.8 and 17.6 pounds per gallon; in the second, both weighed 15.9. Both results were far off the 14.5 target, and both showed serious instability. The Chief Counsel's report concluded the tests should have told Halliburton's technical staff that the cement it planned to pump at Macondo was likely unstable. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17)

Halliburton did not report any of the February test data to BP until March 8, and the official data report included only the second of the two failed tests. Nobody stopped the job. In April the pattern repeated. On April 1, Morel emailed Halliburton that "this is an important job and we need to have the data well in advance to make the correct decisions on this job." Halliburton's lab finally ran a fresh foam stability test on April 13, a week before the blowout, using rig samples and a recipe nearly identical to what would be pumped. The cured sample weighed 15.7 pounds per gallon at the top and 15.1 at the bottom, again far off the 14.5 target, again seriously unstable. When Gagliano emailed BP's engineers the official laboratory reports on April 17, they included neither that test nor any foam stability test at all, and he did not otherwise alert BP to the results. The cement was pumped two days later. When the final slurry was pumped on April 19 and 20, it was this foamed design, about 60 barrels of it, a small volume for a well that size, pushed into place at deliberately low rates to protect the weak rock. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17)

While the casing went in the hole, there had been one more warning, this one audible. When the crew tried to start circulating mud through the float collar at the bottom of the casing, a one way valve assembly that was supposed to convert under modest pressure, nothing moved. They pressured up nine times: 1,800, 1,900, 2,000, 2,250, 2,500, then 2,750 and 3,000 psi. At 3,142 psi the pressure suddenly dropped and circulation began. The National Academy of Engineering noted that converting the equipment had been expected to take about 700 psi; the force actually needed was more than four times that, possibly because debris had plugged the valve. What exactly happened at the bottom of the well in those minutes, whether the float collar was crushed, the shoe track ruptured, or the rock itself broke down, was never established. It was an anomaly, unexplained, and the job went on. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo Well-Deepwater Horizon Blowout: Lessons for Improving Offshore Drilling Safety - National Academy of Engineering (2011)

Even the cement's height had been shaved down. The main reservoir at Macondo began at 18,100 feet, and BP estimated the top of the hydrocarbon zones at 17,803 feet; its engineers decided to pump only as much cement above the zones as the MMS required, and on about April 14 fixed the top of cement at 17,300 feet, leaving 503 feet of cement above the highest zone. The decision went in through a management of change review that Hafle marked high priority and asked to have approved by the next day. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17)

Last came the decision about checking the work. A cement bond log, run on a wireline down the casing, uses acoustics to show whether cement has set solidly around the pipe. On April 18 and 19, a team of Schlumberger technicians flew out to the rig to run one. BP told them the log would be run only if there were lost returns. On the morning of April 20, having seen no lost returns and a successful lift pressure, BP concluded the cement job had gone well enough and sent the Schlumberger team home; their helicopter left at about 11:15 a.m. Skipping the log saved about eight hours of rig time. The well's last independent barrier check flew away before lunch. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo Well-Deepwater Horizon Blowout: Lessons for Improving Offshore Drilling Safety - National Academy of Engineering (2011)

Five decisions: the long string, the short circulation, the six centralizers, the untested foam, the cancelled log. BP's own engineering technical practices, updated in 2009, called for centralized pipe reaching 100 feet above the highest permeable zone in a well; at Macondo almost nothing was centralized at all. Every one was signed off by professionals who believed they were managing risk, and most of them involved a trade in which schedule and cost sat on one side of the scale. The presidential commission, reviewing the record, found that the cementing failures at Macondo flowed from exactly these choices, made in sequence, under pressure, on a well that was six weeks late. The Chief Counsel's team found no sign that any one person, in Houston or on the rig, ever reviewed the combined effect of those risks, or even communicated them to the other contractors on the well; BP, the report said, treated risk factors as surmountable and then forgettable. Macondo: The Gulf Oil Disaster - Chief Counsel's Report (2011-02-17) Macondo Well-Deepwater Horizon Blowout: Lessons for Improving Offshore Drilling Safety - National Academy of Engineering (2011)