Unfinished reckoning

24 October 2026

When the second report was laid before Parliament on 4 September 2024, the Prime Minister rose to answer it with an apology. On behalf of the British state, Keir Starmer said sorry to each and every one of the bereaved and to all the families affected: it should never have happened; the country failed to discharge its most fundamental duty, to protect you and your loved ones, the people we are here to serve; and I am deeply sorry. He quoted the report's own verdict back at the Commons, the decades of failure by central government, and named what seven years had meant to the families: still waiting for the justice you deserve, let down so badly, before, during and in the aftermath of this tragedy. The apology covered the state. It could not cover the rest, and everyone in the chamber knew it. Prime Minister's statement on Grenfell Tower Inquiry final report: 4 September 2024 - GOV.UK

Grenfell United, speaking for the bereaved and survivors on the day the report came out, accepted the findings and looked past them in the same breath: at the heart of the report is the fact that 72 people lost their lives, and the group has an expectation that the Metropolitan Police and the Crown Prosecution Service ensure that those who are truly responsible are held to account and brought to justice. Their statement spoke of a painful six years listening to the evidence of the deaths of fifty four adults and eighteen children, and it refused the consolation that something merely malfunctioned: "The system isn't broken, it was built this way." Their lawyers had told the inquiry that the corporate core participants, Arconic, Kingspan and Celotex, were "little better than crooks and killers", and the group said the report made clear that the statement was entirely true. It set its own summary against the state's: every single loss of life was avoidable, the time to address this is already three decades too late, and Arconic, Kingspan, Celotex and Rydon should be banned from central and local government procurement. That expectation has organised everything since. Publication of the Phase 2 report - Grenfell United statement (2024-09-04)

At least the machinery of the state now publishes its own scorecard. In September 2025 the government issued its second progress report on the inquiry's recommendations, recording that it had accepted all of the findings and would act on all fifty eight Phase 2 recommendations; of the sixty one recommendations across both phases, its table showed fifty eight in progress and three complete, the three all sitting among the recommendations on vulnerable people and phase one. The same month, the Minister for Building Safety appointed Thouria Istephan, who had sat on the inquiry panel itself, as interim Chief Construction Adviser for twelve months. It is the report's own remedy arriving a year behind itself: the inquiry had recommended that the Secretary of State appoint a Chief Construction Adviser with a sufficient budget and staff to provide advice on all matters affecting the construction industry. A scorecard is not a remedy, and the numbers that matter most sit in another publication entirely. Grenfell Tower Inquiry: Government progress report September 2025 - summary update - GOV.UK Grenfell Tower Inquiry: Phase 2 Report Overview (2024-09-04)

That publication is the monthly remediation data release, and its August 2026 edition reads like the country's unfinished business rendered in tables. As at the end of August 2026, 4,724 residential buildings of eleven metres and over had been identified with unsafe cladding whose progress is being reported on, an increase of twenty seven in a single month, and that number is itself only an estimated sixty five to eighty one per cent of the buildings expected eventually to enter the programme. Of the monitored buildings, 2,571, fifty four per cent, had either started or completed remediation works; 1,849, thirty nine per cent, had completed. An estimated 1,100 to 2,600 buildings over eleven metres are expected to require remediation but have yet to be identified. The original ACM core, the buildings most like Grenfell's own, is further along: of the 516 high rise residential and publicly owned buildings of eighteen metres and over with ACM cladding systems unlikely to meet Building Regulations, 503, ninety seven per cent, had either started or completed works by the end of August 2026, and of the 640 high rise buildings proceeding through the Building Safety Fund, 490, seventy seven per cent, had completed remediation. Nine years after one building burned, the state cannot yet say how many buildings it is making safe. The split inside the programme tells its own story about who moved fastest: every one of the 165 social sector residential buildings in the ACM programme had started or completed remediation, against ninety five per cent of the 249 private sector ones, and eighty eight per cent of buildings proceeding with a Building Safety Fund application had started or completed works. Where persuasion failed, compulsion has begun: as at 31 August 2026, local authority enforcement action under the Housing Act 2004 had been, or was being, taken against 929 buildings over eleven metres with suspected unsafe cladding. The bill, as the department's best estimate of March 2025 renders it, runs to between 11.8 and 22.7 billion pounds to remediate every residential building of eleven metres and over in England that has or had unsafe cladding, with government programmes carrying 6.7 to 15.2 billion of it and non government actors 5.2 to 7.4 billion: the developer refunds and the Building Safety Levy counted, in the government's own arithmetic, inside its available 9.2 billion. The scorecard counts five strands of programme at once, combined into one measure of remediation progress: the ACM programme, the Building Safety Fund, the Cladding Safety Scheme, the developer remediation contract and the social sector buildings whose registered providers are self funding. The government's acceleration machinery is named in the same release: a Remediation Acceleration Plan, and alongside it a joint plan to accelerate developer led remediation and improve the experience of residents still waiting. The newest of the programmes, the Cladding Safety Scheme, fully launched in July 2023, shows how far the middle of the stock still has to go: in the August 2026 reading, 1,497 buildings of eleven metres and over had been assessed as eligible for it, 280 of them transferred from the Building Safety Fund, and of those only 417, twenty eight per cent, had started or completed works and 139, nine per cent, had completed, counting those awaiting building control sign off, with a further 2,660 buildings still in the scheme's pre eligible stages. The developers themselves are now inside the scorecard too: as at the end of August 2026, 2,679 buildings of eleven metres and over had been identified with life critical fire safety defects, cladding and non cladding, which their developers have committed to remediate or to pay to remediate, an increase of fifty eight in a month, and of those, developers reported that 1,416, fifty three per cent, had either started or completed remediation works, an increase of 152 in a month, with 613, twenty three per cent, completed, seventeen of them in the final month of the count. From June 2026 the scorecard also takes in the Interim Measures Alarm Fund, the successor to the waking watch funds that paid for patrols and common alarms in buildings whose residents spent years waiting beside the risk. Building Safety Remediation: monthly data release, August 2026 (accessible version) - GOV.UK

Beyond the scorecards sit the asks the machinery has not yet reached. The report recommended that the functions relating to the construction industry, still dispersed, be drawn together under a single regulator, and that the responsibilities for fire safety currently exercised by three departments, housing, the Home Office and business and trade, be gathered into one department under a single Secretary of State. It asked, too, that the government be legally required to keep a public record of the recommendations made to it by public bodies and of its own responses, so that a coroner's letter could never again fall off a shelf that did not exist. From the first report it carried forward the plainest ask of all: that the law require personal emergency evacuation plans for every resident of a high rise whose ability to get out without help may be compromised, with current information about them kept in a premises information box, a remedy for the disabled and vulnerable residents whose own landlord's data systems, the second report records, were not properly co ordinated. And beyond the recommendations stands a warning the report passes on from its own expert witness, Rodney Hancox: the internal gas pipework in some older buildings is not sleeved where it passes through walls and floors, as regulations have required since 1972, and a more active approach to replacement is needed to avoid a serious leak with potentially catastrophic consequences. Grenfell Tower Inquiry: Phase 2 Report Overview (2024-09-04)

What is left of the tower is coming down. On 7 February 2025 the government confirmed that Grenfell Tower would be taken down, through what the official statement called careful and sensitive progressive deconstruction behind the wrapping, a programme likely to take around two years. The engineering advice left little room for sentiment: the tower is significantly damaged, and it remains stable only because of the measures put in place to protect it. The community's answers, faithfully recorded, pulled both ways: some suggested floors should be retained for a memorial, others said that would be too painful. Hamid Ali Jafari, whose father was killed in the fire, told the BBC he feared the removal meant the tragedy would be forgotten. "I feel like they're trying to erase people's memories, that they can't remember what happened, and then they can hide whatever they're doing," he said. "... My dad has two cemeteries; one where we buried him and one is at Grenfell Tower. When the wind blows around the tower, I can feel my dad." Mushtaq Lasharie, chairman of the Lancaster West Residents' Association, spoke for the other half of the street: the overwhelming majority of locals, he said, favoured taking it down, safety concerns left no other option, and they had been waiting for closure for more than seven years. Update on the future of Grenfell Tower - GOV.UK (2025-02-07) Grenfell Tower to be taken down, government confirms - BBC News (2025-02-07)

Around the decision sat the logistics of a slow goodbye. The government promised no changes to the Tower before the eighth anniversary of the fire, and committed to confirming a specialist contractor to develop a detailed plan for taking it down, the work led by technical experts with specific health and safety responsibilities. When the deconstruction begins, specialists will work from the top down, dismantling the tower floor by floor behind the wrapping that has sheathed it for years. By the time of the decision, temporary hoarding had closed off the area around the building for more than seven years, a perimeter that was itself part of the neighbourhood's daily life. Angela Rayner's stated reasoning addressed the memorial question directly: it would not be fair to keep some floors of the building while dismantling others, and doing so, she concluded, would be deeply upsetting for some of the families. Update on the future of Grenfell Tower - GOV.UK (2025-02-07) Grenfell Tower to be taken down, government confirms - BBC News (2025-02-07)

Grenfell United's verdict was blunt: "Ignoring the voices of the bereaved on the future of our loved ones' gravesite is disgraceful and unforgivable." Angela Rayner, the group said, could not give a reason for her decision to demolish the tower, refused to confirm how many survivors and bereaved had been spoken to in the recent short four week consultation, and claimed the decision was based on their views when, judging from the room alone, the vast majority of whom were bereaved, no one supported it. The government's own account of the same months records that the Deputy Prime Minister had met bereaved families, survivors and residents since her appointment the previous July and had told families the November before that she would listen and consider before deciding. Both statements stand as their makers made them; the distance between them is the story of the community's nine years. Decision to demolish Grenfell Tower branded a ‘disgrace and unforgivable’ by group representing survivors - Inside Housing (2025-02) Update on the future of Grenfell Tower - GOV.UK (2025-02-07)

Slowly and on purpose, a decision is taking shape about what will stand where the tower stands. The independent Grenfell Tower Memorial Commission continues its work, and the government statement records the community choosing a design team to work with the Commission on designing the memorial. Update on the future of Grenfell Tower - GOV.UK (2025-02-07) Grenfell Tower Memorial Commission - official site

The criminal answer arrived at its milestone last. On 30 September 2026 the Metropolitan Police announced that it had submitted all of its files to the Crown Prosecution Service for charging decisions on the Grenfell Tower fire: twenty files relating to fifty four people and twenty organisations identified as suspects, together with fourteen overarching evidence files. The files ask the prosecutors to consider charges across the full register of public wrong: corporate manslaughter, gross negligence manslaughter, health and safety offences, fraud and fraud related offences, and misconduct in public office. The Met's summary reports to the prosecutors alone exceed four million words across 12,600 pages, referencing more than 45,000 documents, images and exhibits; the work behind them gathered 165 million electronic files, took 14,700 statements, and catalogued more than 27,000 exhibits, from cladding panels down to screws, nuts and bolts, held in a secure warehouse. The tower was held as a crime scene for fourteen months, with forensic fingertip searches of every flat and communal area and roughly fifteen tonnes of debris examined on each floor. Detectives also examined in detail the work of the public inquiry, including the 1,700 pages of its final report, cross referencing it against their own files to be sure no piece of evidence had been missed. Charging decisions now sit with the prosecutors, and the Crown Prosecution Service has committed to making them before the tenth anniversary of the fire, in June 2027. Deputy Assistant Commissioner Kevin Southworth called the submission a milestone moment for the police work on a tragedy that took the lives of seventy two people, paid tribute to a dedicated team of two hundred and twenty officers, and conceded the wait: nine years to reach this point, in one of the most complex inquiries ever undertaken by any UK law enforcement agency, the scale truly enormous. The time, he said, was necessary to ensure the case was meticulous and presented "the very best possible evidence to the CPS for charging decisions". Met submits all Grenfell files to the CPS for charging decisions - Metropolitan Police (2026)

Meanwhile, the community has kept its own count, in its own way, from the beginning. On the first anniversary of the fire, about five thousand people joined a silent walk in honour of the seventy two, in a neighbourhood that had already been walking in silence on the fourteenth of every month since the fire. Firefighters laid down their helmets and formed a guard of honour as the marchers passed, some stopping to embrace them; a seventy two second national silence was held at midday and observed across the country, including at government buildings and in Parliament. Earlier that day a silent procession had followed a memorial service at St Helen's Church, near the tower, where the seventy two names were read out again. The walks on the fourteenth have continued month after month, year after year, through the inquiry, the reports, the apologies and the waiting: a calendar the state did not set and cannot close. Grenfell Tower fire: Silent walk marks first anniversary - BBC News (2018-06-14)

The open accounts, gathered in one place: the charges not yet decided, the fifty eight recommendations in progress with three complete, the cladding still on buildings and the buildings not yet found, the tower still standing behind its white wrapping while the deconstruction is planned, the memorial not yet designed, and the apology given and acknowledged and incapable of being the last word. Grenfell United said it on the day the last report was published, and nothing since has made it less true: at the heart of all of it is the fact that 72 people lost their lives. Grenfell Tower Inquiry: Government progress report September 2025 - summary update - GOV.UK Building Safety Remediation: monthly data release, August 2026 (accessible version) - GOV.UK Update on the future of Grenfell Tower - GOV.UK (2025-02-07) Met submits all Grenfell files to the CPS for charging decisions - Metropolitan Police (2026) Prime Minister's statement on Grenfell Tower Inquiry final report: 4 September 2024 - GOV.UK Publication of the Phase 2 report - Grenfell United statement (2024-09-04)