Between 2012 and 2016, Grenfell Tower was wrapped in a new skin, and the record of how that skin was chosen is a paper trail of decisions in which fire barely figures. The refurbishment, completed by Rydon Construction in May 2016 at a cost of 8.6 million pounds, was part of a wider transformation of the Lancaster West Estate. The contract between the Kensington and Chelsea Tenant Management Organisation and Rydon was worth 9.2 million pounds, and a list of amendments to it, seen by the Guardian, shows what happened to the tower's cladding after the residents had had their say. Grenfell cladding approved by residents was swapped for cheaper version - The Guardian (2017-06-30) Grenfell Tower: What happened - BBC News

Item by item, the money bought a thorough remaking of a forty year old building: new exterior cladding, replacement windows and a communal heating system, with the bottom four floors remodelled to create seven additional homes and improve the communal facilities. It was the largest intervention in the tower's fabric since it was built, and it touched almost every part of the envelope through which fire would later pass. Grenfell Tower: What happened - BBC News

In 2012, Studio E Architects proposed cladding the tower in zinc panels with a mineral rich, fire retardant polyethylene core, and the residents approved that choice; it stands in the planning papers as the consulted, agreed design. In 2014, the zinc was replaced in the contract with cheaper aluminium panels whose polyethylene core has since proved combustible in government tests. The saving was 293,368 pounds, according to documents seen by the Guardian; the BBC's own documents put it at nearly 300,000 pounds. Contractors working for Kensington and Chelsea council were asked in 2014 to make the switch, the BBC reported, from the zinc the residents had approved to the aluminium they had not. Grenfell cladding approved by residents was swapped for cheaper version - The Guardian (2017-06-30) Grenfell Tower: Cladding 'changed to cheaper version' - BBC News (2017-06-30)

As a specimen of its form, the amendment is a masterpiece. The change is minuted as fitting, in the contract's own words, cassette fix aluminium cladding in lieu of zinc cladding, one line item, indistinguishable on the page from the removal of all external landscaping works, which saved a further 428,000 pounds, and the swapping of window surrounds from birchwood to MDF or softwood, which saved 117,000 more. On paper the tower's skin was one economy among three. Grenfell cladding approved by residents was swapped for cheaper version - The Guardian (2017-06-30)

On the page sat a fire dimension, for anyone who chose to weigh it. A tolerance for fire performance had been set for the project, and both products sat within it; both were certified under the European fire resistance standard. But the aluminium panels were considered the more combustible of the two, and they carried the worse rating for the amount of smoke they would emit. The swap did not break the project's own written rule. It exploited the space inside it. Grenfell cladding approved by residents was swapped for cheaper version - The Guardian (2017-06-30)

On the inquiry's own reading, the paper trail runs in the same direction. Studio E had wanted to use zinc rainscreen panels, the inquiry records, but cost became an increasingly important consideration for the TMO, and eventually the aluminium composite material, Reynobond 55 PE, was chosen largely on the grounds of cost. Rydon was able to offer a substantial saving through the use of aluminium composite panels because of its existing relationship with its intended cladding sub contractor, Harley. Price did not merely prefer the cheaper panel. It organised the relationships that delivered it. Grenfell Tower Inquiry: Phase 2 Report Overview (2024-09-04)

A refurbishment's ordinary machinery carried the decision: the TMO as client, Rydon as builder, and Artelia, a French owned company, wearing several hats at once, as the TMO's project agent coordinating the development of the project's requirements, and as quantity surveyor advising on cost and preparing tender and contract documentation. What the machinery was optimising for is on the record. An urgent nudge email from the TMO's project manager to Artelia about cladding prices read: "We need good costs for Cllr Feilding-Mellen and the planner tomorrow at 8.45am!" Feilding-Mellen was the councillor whose brief covered the refurbishment. Grenfell cladding approved by residents was swapped for cheaper version - The Guardian (2017-06-30)

There was even a rehearsal of the finished product. In the summer of 2014, representatives of the TMO and the council's planners were shown a mock up of the cladding system on site. Minutes of a progress meeting on 15 July 2014, attended by the TMO, Artelia and Rydon, record that the concerns raised were about design, the colours and the fixing detail, which planners were to view two days later, not safety. The same minutes record that Rydon would appoint other consultants, to include fire, disability access and acoustics, only after the main subcontractors were on board. Fire, in the sequencing of the project, was an afterthought to be retained later. Grenfell cladding approved by residents was swapped for cheaper version - The Guardian (2017-06-30)

The machinery's own rules bent where price was concerned. The inquiry records that the TMO manipulated the procurement process to avoid putting the architectural services contract out to public tender, and that it entered into discussions with Rydon before the procurement process had finished, against the advice of its own lawyers that doing so would be improper: the understanding reached was that if Rydon won the contract, it would bring its price down to an acceptable level. Rydon's tender had been judged the most competitive, and it still exceeded the budget. The budget had been in trouble from the beginning: the initial plans ran into difficulty when the estimated cost of the project came in over budget by a significant margin, and in about May 2013 the TMO's emphasis shifted openly from maintaining the momentum of the project to saving cost: the shift that produced the recommendation, reluctantly supported by Artelia, that a principal contractor be appointed through a formal procurement process at all. Grenfell Tower Inquiry: Phase 2 Report Overview (2024-09-04)

Reynobond 55 PE is a simple object with a lethal appetite, manufactured and sold by Arconic Architectural Products. Each panel is two thin sheets of aluminium with a polyethylene core to provide stiffening, manufactured in flat sheets, cut to size and fixed to a metal sub frame, either as flat panels by rivets or as three dimensional structures, known as cassettes, hung by slots and held by gravity. At Grenfell it went up in cassette form. Polyethylene burns fiercely. Behind the panels, the inquiry's account of the system continues, went insulation and cavity barriers: Celotex RS5000, a combustible polyisocyanurate foam, and Lamatherm cavity barriers manufactured by Siderise. Each component had its certificate, its data sheet, its place in the specification. What none of the paperwork modelled was the assembly: the factors that govern how fire spreads over ventilated rainscreen external wall systems are complex, the inquiry observes, understanding them is an evolving science, intuitive judgements are often wrong, and a small change in the system can have a significant effect on the outcome. Grenfell Tower Inquiry: Phase 2 Report Overview (2024-09-04)

Even the pipework ends in the same place. In 2016 and 2017 one of the tower's six gas risers, suffering from corrosion, was replaced, and the inquiry found defects in the design and execution of the work. The Phase 1 report records that some of the works associated with the new riser were incomplete and may have contributed to the spread of smoke, although with the gas shut off at 23.40 on the night of the fire, the riser's contribution to the fire itself appears to have been minimal. A corroded pipe, defectively replaced, running through the building everyone might need to escape: the smallest entry in the refurbishment ledger reads the same as the largest. Grenfell Tower Inquiry: Phase 2 Report Overview (2024-09-04) Grenfell Tower Inquiry: Phase 1 Report Overview (2019-10-30)

Underneath the works, the building's own defences had been allowed to rot. The new front doors installed by the TMO in 2011 and 2012 did not meet the fire resistance standards suggested by Approved Document B, because the TMO had failed to specify the correct fire safety standard when ordering them. Many of the self closing devices on the front doors of flats failed to work effectively, and some were missing entirely; no effective inspection and maintenance programme was ever instituted for them, despite an Enforcement Notice from the London Fire Brigade in late 2015 over ineffective door closers at Adair Tower, another high rise the TMO managed, and a Deficiency Notice in 2016 in relation to Grenfell Tower itself, on the same grounds. The TMO's Emergency Plan for the tower was out of date and incomplete and did not reflect the changes the refurbishment had made, a fact the organisation had been well aware of since a fire at Adair Tower forced the lesson on it. The same plan shaped hole ran through the tower's most vulnerable tenancies: the inquiry would later record that the fire revealed the importance of the responsible person under the Fire Safety Order collecting enough information about vulnerable occupants for personal emergency evacuation plans to be prepared and for their escape to be assisted, and that the TMO had taken only some steps to gather information of that kind. Grenfell Tower Inquiry: Phase 2 Report Overview (2024-09-04)

When the cladding went up, the council side of the borough celebrated a regeneration. When the tower burned, the saving it had signed off became the most examined building material in Britain. Kensington Council leader Nicholas Paget-Brown resigns after fatal Grenfell tower fire - The Independent (2017-06-30) Grenfell cladding approved by residents was swapped for cheaper version - The Guardian (2017-06-30)