On 2 January 2025 the State began moving the waste from the factory to a private treatment, storage and disposal facility in the Pithampur industrial area of Dhar district, about 35 kilometres from Indore. The Hindu put the amount moved at 350 tonnes in March 2025 and 358 tonnes in June; both figures are given as reported. Pithampur saw large protests after the waste arrived, from residents of the town and nearby villages and from Indore, opposing the plan. [24] [29]

The State then did what the High Court had asked: it burned 30 tonnes in three trial runs, at 135, 180 and 270 kilograms an hour, on 27 February to 3 March, 5 to 8 March and 10 to 12 March. It told the court emissions from the stacks had been within prescribed standards. On 27 March 2025 a bench of Chief Justice Suresh Kumar Kait and Justice Vivek Jain allowed the State to burn the remaining waste, at 270 kilograms an hour and under the supervision of the Central and Madhya Pradesh pollution control boards, in about 72 days. [24]

The full burn began on 5 May 2025. By about 1 a.m. on 30 June, 337 tonnes had been incinerated over 55 days, including four days of stoppage for cleaning; 21 tonnes remained to be burned. The pollution board's regional officer told The Hindu that the trials had shown a few problems, with environmental parameters exceeding limits a few times when the waste was broken into pieces and mixed, and that for the full burn the waste was crushed to powder and mixed uniformly. He said air monitoring at two locations showed readings within limits in three neighbouring villages. By that date, 814 tonnes of ash and residue had been collected, with about 850 expected, and it was to be buried in specially built landfills. Twenty one tonnes, mostly soil from the factory site, were still being burned. [29]

The 1989 settlement sorted injuries into categories, and compensation followed the category. Survivor organisations say that many people with lasting illness were placed in the two lowest ones, temporary disablement and minor injury, and were paid accordingly. The Union's own curative petition had described the numbers in those categories as far larger than the Court had assumed in 1989, which the 2023 bench answered by saying the sum still covered them. [17]

On 24 July 2025 a bench of Chief Justice B.R. Gavai and Justice Vinod Chandran gave the survivors' groups liberty to take that claim to the Madhya Pradesh High Court and asked the High Court to decide it on its merits. The Hindu reported that the Supreme Court made clear it had not gone into the merits. The groups, represented by senior advocates Raju Ramachandran and Karuna Nundy and by Prasanna S., had asked the Court to direct the Centre to identify the misclassified survivors and recategorise them under the 1985 claims Act, so that compensation would cover their medical treatment. [34]

The Hindu's report quotes the survivors' petition as saying that the 2023 dismissal made it clear that any shortfall in compensation was a responsibility of the Union government. [34] [17]

Disposal shifted the argument from waste to ash. On 31 July 2025, according to the New Indian Express, the Madhya Pradesh High Court told the State to move the ash to a place without human habitation. [32]

In September 2025, according to Medical Dialogues, the Supreme Court issued contempt notices to the Union Health Ministry and the Indian Council of Medical Research over noncompliance with its orders on medical care. [39] [40]

On 8 October 2025 the High Court repeated its direction to move the ash to a place without human habitation. According to the New Indian Express, the bench of Justices Atul Sreedharan and Pradeep Mittal put the ash at 899 tonnes. The planned containment site was about 500 metres from habitation in Dhar district. The court said that the residual waste was still toxic, and that if the containment structure collapsed in a natural disaster like an earthquake "it would be another disaster in the waiting". It recorded that an intervention application disclosed tests on the ash still showing mercury above permissible limits, as reported in the pollution board's report of 12 August 2025. It said that the State's video presentation of a state of the art structure "doesn't satisfy the court". [32]

Convicted officials have used the appeal to attack the trial itself. In November 2025, the Times of India reported, a Bhopal court was likely to decide on 28 November an application by officials of the Union Carbide plant seeking a retrial. The lawyer for two of them, J. Mukund and S.P. Choudhary, had filed a 92 page written submission calling the CBI charge sheet against the Indian officials "malafide, bogus and unfounded". The CBI and nongovernmental organisations representing survivors answered that the application was not maintainable and that it was an attempt to shift blame to the American parent. [50]

Sources for this read (8)
  1. [24] The Hindu 27 Mar 2025
  2. [29] The Hindu, 337 tonnes of UC waste incinerated, 30 Jun 2025
  3. [17] SC curative judgment 14 Mar 2023
  4. [34] The Hindu, SC asks HC to hear misclassification claim, 24 Jul 2025
  5. [32] New Indian Express, MP HC directs relocation of toxic ash, 9 Oct 2025
  6. [39] Medical Dialogues, SC contempt notices, 29 Sep 2025
  7. [40] TOI, designated bench for medical care PIL, 27 Aug 2026
  8. [50] TOI, city court to decide retrial plea, 10-11 Nov 2025