A cable car, a record season and a court deadline

Published 19 October 2026

On 5 March 2025 the Union Cabinet approved a ropeway from Sonprayag to Kedarnath. The Press Information Bureau described a 12.9 km project under the National Ropeways Development Programme, to be built on a design, build, finance, operate and transfer basis at a total capital cost of Rs 4,081.28 crore. It would use tri cable detachable gondola technology with a design capacity of 1,800 passengers per hour in each direction, or 18,000 a day, and cut travel in one direction from about eight to nine hours to about 36 minutes. Cabinet approves Sonprayag-Kedarnath ropeway, 12.9 km (PIB, 2025-03-05, PRID 2108413) Parvatmala: National Ropeways Development Programme (PIB feature, PRID 2110398)

Reporting the same day, The Economic Times said the Cabinet had also approved a Hemkund Sahib ropeway of 12.4 km at Rs 2,730.13 crore, and that the earlier estimate for the Kedarnath line had been around Rs 1,200 crore for a 13 km route, with estimates since revised. The Economic Times report gave a travel time of 60 minutes against the current six to seven hour trek and a capacity of 3,600 passengers per hour in each direction. Those figures differ from the PIB's, and they are printed here with their owner: the 36 minutes and 1,800 per hour belong to the PIB, and the 60 minutes and 3,600 belong to the Economic Times. Cabinet approves Sonprayag-Kedarnath ropeway, 12.9 km (PIB, 2025-03-05, PRID 2108413) Parvatmala: National Ropeways Development Programme (PIB feature, PRID 2110398) Cabinet approves Kedarnath ropeway project for Rs 4,081 crore (Economic Times, 2025-03-05)

By June 2026 the ropeway was moving through its surveys. News9 reported that the second board meeting of Uttarakhand Ropeway Development Limited, chaired by Chief Secretary Anand Bardhan, reviewed the Kedarnath and Hemkund Sahib projects and pushed the forest clearances; National Highways Logistics Management Limited told the board that the LiDAR survey and videography for the Kedarnath project were complete, geotechnical surveys for the Gaurikund and Sonprayag stations were done, the preliminary alignment was finalised and the final alignment was expected by the end of June 2026, and a logistics dry run with full sized containers from Dehradun to Sonprayag had been carried out to test how construction material would move. The board also directed parking, last mile connectivity and commercial zones around the stations, with continuous engagement of local residents and businesses. Kedarnath and Hemkund Sahib Ropeway Projects Accelerated, Chief Secretary Reviews Progress, News9media

A tender for independent engineer services for the ropeway, listed on a tender portal with an estimated cost of Rs 3,876.53 crore, carried corrigenda in 2026 that extended the bid due date. That estimate is another figure from another owner, and the listing does not explain how it relates to the Cabinet's sum. NDTV reported that the ropeway would be developed by Adani Enterprises Limited at an estimated Rs 4,081 crore, and that pilgrims at the time trekked about 19 km from Gaurikund, with helicopter services from Phata and Sersi. A priest and secretary of the Kedarnath Sabha, Umesh Chandra Posti, said the ropeway would allow even those unable to trek to visit the shrine. On 22 June 2026 the board of Uttarakhand Ropeway Development Limited met under the Chief Secretary, Anand Bardhan, who stressed expediting forest land clearances and utility shifting for both ropeway projects, according to News9. NIDM, India Disaster Report 2013 CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand Kedarnath and Hemkund Sahib Ropeway Projects Accelerated, Chief Secretary Reviews Progress, News9media 'Make Yatra Easier': Devotees Seek Early Completion Of Kedarnath Ropeway, ndtv.com (2026; text mirror-verified)

Three lengths are quoted for the trek in these sources. TV9 in January 2026 wrote of a 16 km trek from Gaurikund, with 9 km to Rambada, 2 km to Lincholi and 5 km to the temple, and reported a seven kilometre tunnel project that would shorten it to 5 km. NDTV said about 19 km, and Dialogue Earth in 2023 wrote of a 14 km route destroyed in 2013. The route has been rebuilt more than once, and each outlet measures from its own starting point. Kedarnath: a decade after the floods, is it safer? 'Make Yatra Easier': Devotees Seek Early Completion Of Kedarnath Ropeway, ndtv.com (2026; text mirror-verified) Kedarnath pilgrimage revamp: Tunnel project to cut trek route from 16 km to 5 km (TV9 English, 2026-01-07)

Yamunotri and Gangotri opened on 30 April, Kedarnath on 2 May and Badrinath on 4 May: so began the 2025 season. On Sunday 15 June, a helicopter carrying pilgrims from Kedarnath to the Guptkashi helipad crashed near Gaurikund at about 5.20 am, killing seven, including the pilot, according to the Economic Times. The report called it the fifth helicopter accident on the Char Dham route since the yatra began on 30 April. It named the pilot as Captain Rajvir Singh Chauhan, 39, and said a representative of the temple committee was among the dead. The Economic Times, citing the Press Information Bureau, said an Aryan Aviation Bell 407 was carrying them, that the preliminary indication was controlled flight into terrain with the helicopter airborne in poor visibility, and that the exact cause would be determined by the national aircraft accident bureau. The state suspended Aryan Aviation's operations and all helicopter operations for two days. economictimes.indiatimes.com, Badrinath doors close for winter as Chardham Yatra ends with 51 lakh pilgrims; Kedarnath leads turnout, 2025-11-25 economictimes.com, Seven killed in helicopter crash near Gaurikund in Kedarnath, 2025-06-15

A month later, on 13 July 2025, the Times of India reported the Wadia Institute's reply to an information request by the Dehradun activist Amit Gupta. It said the Chorabari glacier was retreating at an average of nearly 7 m per year, and that its ice covered area shrank from 6.1 sq km in 2009 to 5.91 sq km in 2019. The paper wrote that the 2013 breach killed over 4,000 people and destroyed more than 3,300 homes. Manish Mehta of the institute said many other Himalayan glaciers were also steadily retreating. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 'Chorabari glacier near Kedarnath retreating 7m per year'

On 12 July 2025 the same paper reported that the Uttarakhand High Court had directed the state to decide, within nine months, on compensation and rehabilitation of residents who lost homes near Kedarnath in 2013. Justice Manoj Tiwari's single bench acted on a petition filed in July 2016 by Hem Chand, Bose Mohan and Arjun Kumar, which was dismissed on 23 July 2020 for non appearance and restored in May 2023 with costs of Rs 2,000. The court accepted the state counsel's suggestion that the petitioners submit a representation, which the state must decide within nine months if made within three weeks. The court observed that the authorities had not yet assessed the petitioners' claims. The article gave the toll as more than 4,000 and the homes destroyed as over 3,300, and said many families remain without permanent rehabilitation. Supreme Court judgment, Char Dham highway project (14 December 2021) HC gives Uttarakhand 9 months to finalise rehab plan for 2013 Kedarnath flood victims

Then the monsoon of 2025 cut into the pilgrimage. Hindustan Times, carrying PTI, reported on 9 October that the Char Dham yatra had been on a downward trend since the Dharali disaster on 5 August, that disasters at Dharali, Sayanachatti and Tharali within 20 days had nearly derailed it, and that the yatra was suspended for four days in the first week of September. By 4 August 41.61 lakh pilgrims had done the yatra, and by 8 October the total was 47.39 lakh. At Kedarnath, 16.56 lakh had come by 8 October, over 4,000 more than the previous year, with 14 days to go before the temple's doors closed. On that Wednesday alone 5,614 visited Kedarnath, 5,042 Badrinath, 6,217 Gangotri, 2,360 Yamunotri and 498 Hemkund Sahib. hindustantimes.com, 16.56 lakh devotees visit Kedarnath; Chardham Yatra regains pace (PTI), 2025-10-09

For the same day, the state's own emergency centre gave a slightly different Kedarnath figure. Organiser, citing the Uttarakhand Emergency Operations Centre, wrote on 9 October that 16,52,076 pilgrims had prayed at Kedarnath so far, and 47,29,555 had completed the Char Dham yatra between 4 May and 7 October, with 14,48,785 at Badrinath and 16,50,925 at Kedarnath in the same listing. That is 16.52 lakh against the PTI report's 16.56 lakh, and the listing's own Kedarnath line of 16,50,925 differs again. The temple doors were to close on 23 October, which coincided with Bhai Dooj. hindustantimes.com, 16.56 lakh devotees visit Kedarnath; Chardham Yatra regains pace (PTI), 2025-10-09 organiser.org, Kedarnath Yatra 2025 sets new record with 16.52 lakh pilgrims; over 47 lakh complete Char Dham Yatra so far, 2025-10-09

On 25 November the season closed, Badrinath's doors shutting with 7,253 pilgrims present, according to the Economic Times. Tourism department data put the total at 51,06,346 for the Char Dham shrines, including 2.74 lakh at Hemkund Sahib, which was 3,02,131 above the previous year's 48,04,215. Kedarnath had the highest footfall at 17.68 lakh, ahead of Badrinath at more than 16.60 lakh, Gangotri at 7.58 lakh and Yamunotri at 6.44 lakh. The two Kedarnath figures, 16.56 lakh on 8 October and 17.68 lakh at season's end, come from the PTI report and the tourism department data respectively, and the first was a count taken before the final three weeks. In 2018 officials had already reported an all time high for the shrine by 16 June: more than 5.5 lakh pilgrims. Polls ahead, shrine rebuilding picks pace economictimes.indiatimes.com, Badrinath doors close for winter as Chardham Yatra ends with 51 lakh pilgrims; Kedarnath leads turnout, 2025-11-25 hindustantimes.com, 16.56 lakh devotees visit Kedarnath; Chardham Yatra regains pace (PTI), 2025-10-09

On 24 October, The Times of India reported that 17.68 lakh pilgrims visited Kedarnath that year, against 16.52 lakh the year before, as the doors of Kedarnath and Yamunotri closed on Thursday for the winter. It put Yamunotri at 6.44 lakh against 7.1 lakh the year before and the four shrines at over 50 lakh. The doors closed at 8:30 am after rituals led by the chief priest, Bagesh Ling, with the Army band playing, in front of about 10,000 devotees. That paper wrote that the increase was 1.25 lakh, which differs from the 1.16 lakh difference between its own two numbers, and the paper's wording is kept as it stands. Uttarakhand: This year, Kedarnath hosted 1 lakh more pilgrims than last year; Char Dham yatra sees 50 lakh dev

Had the rules held, the numbers the season set would have been against them. Hindustan Times, marking ten years since the disaster in July 2023, reported that an expert panel constituted by the Supreme Court had suggested in 2014 that no more than 5,000 people a day be allowed at Kedarnath, 6,000 at Badrinath, 3,500 at Yamunotri and around 4,000 at Gangotri. The state government did impose a daily limit, the paper reported, then revoked it on 21 April on the eve of the pilgrimage; the limits it had announced were 500 for Yamunotri, 9,000 for Gangotri, 15,000 for Badrinath and 18,000 for Kedarnath, higher on three of the four routes than the panel's suggestion, the exception was Yamunotri, where the announced limit of 500 a day sat below the suggested 3,500. The paper also noted that in 2014, soon after the tragedy, the Supreme Court appointed expert body had said hydropower projects should not be built in disaster prone valleys north of the main central thrust line, and that an interministerial group had recommended such areas be left pristine; neither recommendation was adopted. Hemant Dhyani, an environmentalist and a member of the Supreme Court appointed panel, told the paper that a sustainable and decentralised model of tourism based on the ecological carrying capacity of the Himalayas was the lesson, and that instead a rampant increase in pilgrim influx was overburdening fragile valleys; he linked the disregard to the 2021 Rishi Ganga flood and the sinking of Joshimath, and said Uttarakhand needed to seriously plan for and take care of its carrying capacity. Anoop Nautiyal, a Dehradun based social activist, told the paper there was a mad scramble to set new pilgrim arrival records, that more than 400 villages displaced by development awaited rehabilitation, and that if tourism and construction were not curbed a tragedy like 2013 could happen again. These are the panel member's and the activist's assessments, printed as such. hindustantimes.com, Ten years of Kedarnath tragedy: Lessons not learnt and challenges ahead, 2023-07-16