By the end of 2016 the plan for the roads was before the courts as well as the ministries. The High Court's order of 19 November 2016 had included directions on bridges and roads, and it reached the Supreme Court in the new year. Business Standard reported on 9 January 2018 that the Supreme Court, with Chief Justice Dipak Misra and Justices A M Khanwilkar and D Y Chandrachud, stayed the order and issued notice to the petitioners who had been before the High Court. The appeal had been filed through the advocate Farukh Rasheed, who argued that the High Court had erred in passing mandatory directions that did not fit the guidelines of the National Disaster Management Authority and the state disaster response fund for rehabilitation. business-standard.com, Kedarnath tragedy rehabilitation:SC stays Uttarakhand HC order, 2018-01-09

In that appeal, the state's figures are a record of what it said the road network had lost. Of 2,072 damaged roads and 258 damaged bridges, it said, 2,068 roads were reopened to traffic in a short time, and the four roads completely washed away were proposed to be reconstructed. Of the bridges, 136 had been repaired, 21 locations needed no reconstruction because of alternative connectivity, and 101 washed out bridges remained to be rebuilt, of which 25 had been and 10 were under construction. The state added that the Asian Development Bank and the World Bank had approved funding for a disaster relief project for roads and bridges to rebuild and strengthen 866 roads of 3,567 kilometres at Rs 970.30 crore over four years. business-standard.com, Kedarnath tragedy rehabilitation:SC stays Uttarakhand HC order, 2018-01-09

As the report listed them, the High Court's directions had asked the state to finish 10 bridges within one year and the tender process for 16 bridges within two months, with the remaining 49 damaged bridges to be rebuilt within a year and four washed out roads within two years. They also covered 141 roads of 966 kilometres approved by the World Bank and 60 roads approved by the Asian Development Bank, with formalities to be completed within two years. Business Standard wrote that, according to the state government's plea, the death toll was estimated around 10,000 with over 3,000 persons missing. That is another toll from another owner: the state's own plea, as the newspaper reported it. Hindustan Times carried the same story of the stay under a headline about rehabilitation. business-standard.com, Kedarnath tragedy rehabilitation:SC stays Uttarakhand HC order, 2018-01-09 hindustantimes.com, Kedarnath tragedy rehabilitation: Supreme Court stays Uttarakhand High Court order, 2018-01-09

Already under way was the audit that would reconstruct the money. The Comptroller and Auditor General's team held an entry conference on 27 April 2017 with the Secretary of the Disaster Management Department, audited May to November 2017, and held an exit conference on 1 February 2018. It sampled five of the 13 affected districts, 90 of 143 implementing units and 483 works costing Rs 1,681.52 crore out of 2,359 sanctioned works of Rs 4,122 crore, which is 20 per cent by number and 41 per cent by cost. Its Report No. 2 of 2018 was tabled on 22 February 2019. NIDM, India Disaster Report 2013 World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand Polls ahead, shrine rebuilding picks pace

An earlier performance audit had already said the harsher thing. Tabled in the state assembly's session at Gairsain on 3 November 2015 and reported by the Times of India, the CAG's audit of the 2013 disaster held that the government's unpreparedness and slow response had aggravated the calamity, that the machinery had no clue about the situation between 15 and 17 June and responded only on 18 June when a team reached by helicopter, and that the State Disaster Management Authority had been virtually non functional since its inception, with the state executive committee's inactivity leaving mitigation funds unassessed at state and district levels. The report noted that landslides at Uttarkashi and Rudraprayag in 2012 had killed 92 people without corrective measures following, that it had failed to frame a policy on explosives despite its own Disaster Management and Mitigation Centre recommending a ban after the 2012 Ukhimath landslide, and that the Uttarakhand Flood Plain Zoning Act of 2012 had not been used to keep construction away from rivers and streams. The Times of India's account puts the officially declared dead in that report's frame at over 4,000 and the houses destroyed at above 19,000. Uttarakhand govt unpreparedness and slow response aggravated 2013 disaster, says CAG report

Prime Minister Narendra Modi laid foundation stones in October 2017 for five projects at Kedarnath, as Hindustan Times later described them: widening of the approach road, a ghat and retaining wall on the Mandakini and Saraswati rivers, houses for the purohit community, a museum and a samadhi of Adi Shankaracharya. He said that there would be "no dearth of funds" and reached out to the corporate sector to join in. The paper said the Prime Minister's Office monitored the work, with Modi reviewing progress through three camera mounted drones over teleconference, and the state's chief secretary, Utpal Kumar Singh, receiving a live feed. In 2018 the town had recorded more than 5.5 lakh pilgrims by the time of that review, which Singh described as the number the shrine used to receive in an entire yatra season. The yatra had begun on 18 April, with the portals of Kedarnath and Badrinath opening on 29 and 30 April. Polls ahead, shrine rebuilding picks pace

Counterpoint arrives in these years: the audit's findings. The Comptroller recorded that by 31 March 2018 the state had completed 2,066 of 2,359 works, or 87 per cent, with 256 in progress and 37 unstarted. The first measure it used was the sanctioned dates, and by those dates, 31 March 2017 for most lines and 31 December 2017 for World Bank works, only 1,769 works, or 75 per cent, had been completed. The report notes that the Medium and Long Term package was meant to be delivered in a time bound manner, and that in practice many departments such as irrigation, forest and public works failed to assess their damaged assets correctly, so that some works were left out of the package while others that had not been damaged were taken up. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand

Money is where the audit was most specific. The total approved outlay was Rs 6,259.84 crore, of which only Rs 4,617.27 crore, or 74 per cent, was made available for projects, and the implementing agencies used Rs 3,708.27 crore, or 59 per cent of the outlay. The Comptroller said that the Government of Uttarakhand did not contribute its Rs 69.91 crore share for the Special Plan Assistance projects, and that it diverted Rs 294.64 crore, 6.38 per cent of the releases. It found that utilisation certificates were inflated, with Rs 61.64 crore claimed against Rs 33.94 crore of actual expenditure. It also noted portions of road works repaired more than once under different funding sources, idling of funds with implementing units, and expenditure in violation of prescribed norms. The money value of its observations was Rs 642.83 crore, which is 38.23 per cent of the total value audited. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand

For Kedarnath itself the audit is a ledger of specific works. The Government of India approved Rs 455.09 crore for the shrine, township and other facilities out of a state demand of Rs 525 crore, with the state to add Rs 69.91 crore, which it did not do. The State Government did not sanction funds for a ropeway between Gaurikund and Kedarnath, for the second phase of the Kedarnath township, for development of other Dhams or for 10 industrial training institutes, though it had received Rs 319.75 crore under the plan assistance. Of 56 works costing Rs 250.43 crore on the Kedarnath yatra route, 40, or 71 per cent, were complete in March 2018, 14 were in progress and two were not started. Financial progress was Rs 169.30 crore, or 68 per cent. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand

How the works went is visible in the cottages and the parking terminal. A state construction corporation, UPRNN, had been assigned 120 cottages at Rs 29.72 crore for pilgrim lodging at Kedarnath in October 2015, and by March 2018 only 92 had been built and none handed over because minor work remained. The furniture, Rs 2.42 crore worth, had been bought in April 2016 and, according to an April 2017 report of the district administration, was not stored in a safe place. A multilevel parking and administrative block at Sonprayag, Rs 65 crore, was assigned in October 2015 but started only in November 2016, and stalled after Rs 38.57 crore of foundation work because a river side flood protection wall by the Irrigation Department had not been built, though it was sanctioned in July 2017. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand

At Uttarkashi, the Nehru Institute of Mountaineering had the demolition and the purohit houses. A committee of the Rudraprayag district administration decided that unsafe buildings, or those in the main path of the shrine, should be demolished for the planned Kedarpuri township, at Rs 70 crore. The state sanctioned phase one of Rs 38.63 crore in September 2016, which included demolition, a temporary store and the reconstruction of 113 buildings for tirth purohits, but phase two was not started for want of funds. By September 2017 the institute was rebuilding only 40 houses, with Rs 12.67 crore spent, and said the remaining 73 could not begin because designs and agreements with beneficiaries were unfinished and land was not allotted. Three bridges at Rs 6 crore were sanctioned in June 2015, and only one, at Rs 1.98 crore, was built by March 2018. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand

Across the whole package the audit found money idle, overclaimed and mispriced. Unspent balances of Rs 30.62 crore of Government of India funds received under the special plan assistance and the state disaster response fund remained blocked with project implementing agencies and were not refunded. The inflated utilisation certificates counted above sat with contract management for roads and bridges, civil aviation and flood protection works that the auditors found deficient, causing unjustified, additional or excess expenditure of Rs 9.03 crore, and the auditors counted an undue benefit of Rs 5.96 crore to contractors through overpayments of Rs 1.55 crore, liquidated damages of Rs 4.25 crore never levied and labour cess of Rs 0.16 crore never deducted. The state created an avoidable interest liability of Rs 19.88 crore, the report says, by not surrendering Rs 274.29 crore of unutilised plan assistance out of Rs 1,100 crore and by not drawing the Asian Development Bank loan of Rs 1,110 crore on schedule, leaving Rs 373.50 crore unused. Each figure is the Comptroller's, from Report No. 2 of 2018. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand

Disaster preparedness was weaker still on the audit's own measure. The targets were 5 helidromes, 19 heliports, 34 helipads and 37 multi purpose halls, and the civil aviation authority built only 27 helipads and no halls in the severely affected districts. Most activities under the World Bank technical assistance project for capacity building were yet to start. The State Executive Committee met twice in 2016 to 2017, the High Powered Committee 52 times from 2013 to 2014 to July 2017, and the district authorities had no monitoring cell for reconstruction and could show no documents of reviews. No separate and centralised mechanism supervised quality, and the Public Works Department's quality control unit graded 61 per cent of road works poorly. CAG Report No. 2 of 2018, Performance audit on Reconstruction of Infrastructure Post 2013 Disaster in Uttarakhand