The shrine rebuilt, the geologists unconvinced
Published 19 October 2026
By 2019 the rebuilt town had a political clock attached to it. Hindustan Times reported in 2018 that the countdown to the 2019 general election had begun and that pressure was piling on the Uttarakhand government to speed up reconstruction and beautification in the shrine town and valley. At least seven major reconstruction and beautification works were then in progress. The paper described the work at Kedarpuri as one of the Prime Minister's pet projects, likely to be one of the poll planks, and said there was no clarity on a deadline even as officials claimed immense pressure to finish. Polls ahead, shrine rebuilding picks pace
Narendra Modi spent a day in a meditation cave, the Rudra cave about a kilometre from the shrine, in May 2019, according to a Hindustan Times report of the video review a year later. In that review, held through a camera mounted drone by video conference from New Delhi, Chief Minister Trivendra Singh Rawat told the Prime Minister that the state needed Rs 200 crore for construction works in the Kedarnath area. The chief secretary gave the schedule. The Adi Shankaracharya samadhi would be complete by 31 December 2020, the Saraswati ghat by 30 June 2020, the Mandakini bridge by 31 March 2021, three caves around the shrine by September 2020, and a bridge on the path to the Bhairav temple was already done. Seventy three houses for priests, in five blocks of which two were finished, would be ready in September, and an open museum was planned. The Chief Minister reported that the yatra was then open only to locals and in a limited way, with devotees asked to wear masks and follow social distancing. Polls ahead, shrine rebuilding picks pace 'Focus on spiritual legacy': PM Modi in review of Kedarnath reconstruction work
Along the path from Rambada to the shrine, the Prime Minister asked that information on the historical, spiritual and religious legacy of Kedarnath be put, and said more spirituality related works could be undertaken. He told the state to identify what needed to be completed first, and said the Centre would provide all possible help for reconstruction at Kedarnath and Badrinath. The same article recalled the October 2017 foundation stones for five projects. Polls ahead, shrine rebuilding picks pace 'Focus on spiritual legacy': PM Modi in review of Kedarnath reconstruction work
In the same years, the search for the missing went on. In September 2020, Hindustan Times reported that on 16 September ten teams of police, state disaster response personnel and health officials began a five day search along the trek route for the remains of the 3,075 people said to have died in 2013, and on Sunday 20 September they found the remains of four persons between Garud Chatti and Gau Mukhda. That September, the state government constituted a high level multi institutional expert committee, headed by the inspector general of the SDRF, to suggest technology and methodology for searching for the remains, and gave it two months to report. The Rudraprayag superintendent of police, Navneet Singh Bhullar, said DNA samples were taken, last rites would be held at Sonprayag, and the samples would later be matched with family members of the missing; the teams had been equipped with body bags, trekking gear and other tools for the search along the trekking route towards the shrine, and another round would resume after fresh directives. The paper's tally of bodies and skeletal remains recovered from the area was 699 before that day, made up of 545 in 2013, 63 in 2014, three in 2015, 60 in 2016, seven in 2017 and 21 in 2018, and 703 with the four. The search was resumed, it said, after repeated directions from the High Court that bodies be recovered for last rites, and the case had begun with a public interest petition filed in 2014 by the Delhi activist Ajay Gautam. hindustantimes.com, Skeletons of 4 missing in 2013 tragedy found in search ops in Kedarnath area, 2020-09-20
On 5 November 2021 the Prime Minister was due at Kedarnath, as the Press Information Bureau announced, to offer prayers, inaugurate the Adi Shankaracharya Samadhi and unveil the statue, and to address a public rally. The Samadhi, it said, had been reconstructed after the destruction of the 2013 floods. He would also inaugurate projects completed at a cost of over Rs 130 crore, among them the Saraswati retaining wall, Aasthapath and ghats, the Mandakini retaining wall and Aasthapath, houses for the tirth purohits and the Garud Chatti bridge on the Mandakini. He would lay the foundation stone for projects worth over Rs 180 crore, among them the redevelopment of Sangam Ghat, a first aid and tourist facilitation centre, an administrative office and hospital, two guest houses, a police station, a command and control centre, queue management and a rain shelter. The release said the whole reconstruction was under the personal guidance of the Prime Minister, who had constantly reviewed and monitored it. It also listed works the Union tourism ministry had completed under its integrated development of Kedarnath scheme. pib.gov.in, PM to visit Kedarnath on 5th November and inaugurate Shri Adi Shankaracharya Samadhi (PRID 1767251), 2021-10-28 pib.gov.in, PM to visit Kedarnath on 5th November; reconstruction started in 2014 (PRID 1769206), 2021-11-03
A ThePrint report of 13 December 2021, five weeks after that event, quoted the state's tourism secretary Dilip Jawalkar, who was the nodal officer for the reconstruction, saying the master plan works would be over by the end of the 2022 pilgrimage season. He said there were limited months of work, six to seven a year, because of the extreme weather and fragile terrain, and that these months coincided with the Char Dham pilgrimage. Work in Kedarpuri had reached the halfway mark, with a multi facility hospital and a sewage treatment plant still to be completed. Nikul Shah of INI Design Studio, which prepared the master plan, said the studio was also responsible for conceptualising and installing the statue of Adi Shankaracharya behind the temple. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 Kedarnath Masterplan, INI Design Studio Kedarnath reconstruction: PM's dream project to be ready by 2022, but experts warn of huge risks, theprint.in (2021-12-
With the plan, the geologists did not agree. ThePrint quoted D P Dobhal, a retired glaciologist of the Wadia Institute of Himalayan Geology, saying the construction was being done on the debris deposited by the 2013 floods in a V shaped valley that is "highly fragile and unstable terrain." "Debris should have been allowed to settle down for a minimum 8 to 10 years before resorting to construction works," he said, and the Mandakini and the Saraswati had changed their courses after 2013 and had shallow beds, so that even three tier protection walls would not help if a 2013 like event recurred. A senior Wadia scientist, who spoke on condition of anonymity, said a report the institute presented to the state three months after the disaster "categorically forbids" construction at Kedarpuri, and that the Geological Survey of India prepared a similar one. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 Kedarnath Masterplan, INI Design Studio Kedarnath reconstruction: PM's dream project to be ready by 2022, but experts warn of huge risks, theprint.in (2021-12-
Nikul Shah answered for the plan. He said it was prepared with due care to keep the human load minimum, that its vision was "de densification of the holy island," and that the sewage treatment plant was being built outside the island so that effluents would be channelled through pipelines to a distant plant. Those are two accounts of the same site, one by the person who drew it and the other by scientists who studied the ground, and each is a view of what the future might bring and not a measurement. World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 Kedarnath Masterplan, INI Design Studio Kedarnath reconstruction: PM's dream project to be ready by 2022, but experts warn of huge risks, theprint.in (2021-12-
Rediff carried the argument forward in 2023 after the subsidence at Joshimath. It said around Rs 1,000 crore had been allocated for the reconstruction from different organisations, including public sector companies. The first phase had built a concrete road 70 feet wide and 840 feet long connecting the temple to Kedarpuri, an 850 foot three tier retaining wall along the Saraswati and a 350 foot protection cover along the Mandakini. The second phase added a hospital, a theatre, a sewage treatment plant, a new bridge and a pilgrims' ghat at the confluence. A section of the priests, Rediff wrote, objected to the gold plating of the walls of the sanctum, which it said cost over Rs 100 crore and was paid for by a family from Maharashtra. The town planner Bipin Rawat said the reconstruction was monitored by the Prime Minister with inputs from the Prime Minister's Office, so that nobody in the state government dared contradict them. That is a quoted opinion, and the article gives no response from the Office. Badrinath-Kedarnath: Modi Must Relook At Redevelopment, Rediff.com India News
A second construction programme ran in the same years along the roads. The Char Dham highway programme, announced on 23 December 2016, aims to widen roads of about 900 kilometres of national highways connecting the four shrines in Uttarakhand and the Tanakpur Pithoragarh stretch of the Kailash Mansarovar route, at a cost The Hindu put at Rs 12,000 crore. Citizens for Green Doon, a Dehradun environmentalist group, filed an application in the National Green Tribunal on 27 February 2018 against construction of the project. The Supreme Court constituted a high powered committee by its order of August 2019. The committee's report was unanimous except on one question, the width of the road, and the December 2021 judgment records the split. A majority of thirteen members favoured applying a 2012 circular of the roads ministry requiring at least a double lane with paved shoulders on all new widening work, a roadway 12 metres wide: seven metres of carriageway, a 1.5 metre paved shoulder and a one metre earthen shoulder on each side. A minority of five, including the chairperson, held that a 2018 circular should govern, under which hill roads carrying 3,000 to 8,000 passenger car units a day get an intermediate lane of 5.5 metres. A bench of Justices Rohinton Nariman, Navin Sinha and Indira Banerjee accepted the minority view in September 2020 and directed that the 2018 circular alone would apply. On 14 December 2021, a bench of Justices D Y Chandrachud, Surya Kant and Vikram Nath allowed the widening of major portions of the strategic roads to double lane with paved shoulders, citing the defence ministry's need for speedy deployment of men and equipment on the China border, while ordering strict implementation of environment protection measures. The road to Yamunotri from Rishikesh was left out because the ministry had not sought to widen it. NIDM, India Disaster Report 2013 World Bank Project Appraisal Document, Uttarakhand Disaster Recovery Project, 2014 Supreme Court judgment, Char Dham highway project (14 December 2021) thehindu.com, Explained: why has the Supreme Court allowed the Union government to widen all three main Char Dham roads, 2021-12-19
On the tenth anniversary, the Times of India counted what the reconstruction had added and what it cost. Officials told the paper that infrastructure works worth Rs 225 crore had been completed in the first phase, including retention walls on both banks of the Mandakini and the Saraswati, a central street leading to the temple, basic facilities and the statue and samadhi sthal of Adi Shankaracharya, and that a second phase of 21 projects worth Rs 198 crore, including residences for priests and night stay facilities for pilgrims, was to be finished by the end of that financial year. Chief Minister Pushkar Singh Dhami, who performed a havan at the shrine for the dead that morning, put the official death toll at 6,054, his government's figure, and one moreentry in this piece's ledger of counts, and said the turnout of 15.6 lakh devotees in 2022 was the result of the work done. Anil Joshi, an Uttarakhand based environmentalist, gave the paper the counterweight: the state had clearly taken steps for disaster management in the previous year, but Uttarakhand was prone to disasters and they would happen in the future too. timesofindia.ind, 10 yrs of Kedar floods: Safety arrangements upgraded near temple
At the ten year dialogue in Dehradun in 2023, Sundriyal said the authorities had quietly stopped calling the roads "all weather," that Char Dham Marg project boards had been installed at various places because it was not possible to commute for 12 months straight in the high Himalaya, and that the government had a budget to build roads but no budget to stabilise the slopes created by cutting them. He said scientists had warned about this well in advance. That is the view of one geologist, and the court's order of December 2021 is the view of the bench. NIDM, India Disaster Report 2013 Supreme Court judgment, Char Dham highway project (14 December 2021) 10 years of Kedarnath: Things are worsening not improving, experts warn (Down To Earth, 2023-06-21)